Regulation 8 Recovery of costsI1

England and Wales

(1)

The local housing authority may recover costs reasonably incurred by them in taking action—

(a)

under regulation 6(1) from the F1landlord on whom the remedial notice was served; or

(b)

under regulation 10(1) from the landlord on whom the notice under regulation 10(3) was served.

(2)

A demand for recovery of costs under paragraph (1) must be served on the landlord from whom the local housing authority is seeking recovery.

(3)

If no appeal is brought under regulation 9, the costs become payable at the end of the period of 21 days beginning with the day on which the demand is served.

Annotations

Textual amendments

F1

Word in Pts. 2-5 substituted (1.11.2025 for specified purposes, 1.5.2026 in so far as not already in force) by The Electrical Safety Standards in the Private Rented Sector (England) (Amendment) (Extension to the Social Rented Sector) Regulations 2025 (S.I. 2025/1043), regs. 1(2)(b), 3(3)(a)

Commencement

I1

Reg. 8 in force at 1.6.2020, see reg. 1(2)

Notes on the whole SI

Textual amendments

F1

Words in Title inserted (1.11.2025 for specified purposes, 1.5.2026 in so far as not already in force) by The Electrical Safety Standards in the Private Rented Sector (England) (Amendment) (Extension to the Social Rented Sector) Regulations 2025 (S.I. 2025/1043), regs. 1(2)(b), 3(1)