For section 7 of that Act (measure of compensation) there shall be substituted the following section—

“7

In assessing the compensation to be paid by the acquiring authority under this Act regard shall be had not only to the extent (if any) to which the value of the land over which the right is to be acquired is depreciated by the acquisition of the right but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of his, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.”

Notes on Part II

Modifications

C1

Sch. 3 Pt. 2 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), art. 1, Sch. 18 para. 2(3) (with arts. 62, 76, 87)

C2

Sch. 3 Pt. 2 applied (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), art. 1, Sch. 12 para. 2(3)(4) (with art. 40, Sch. 13)