Section 10D CertificationF1
United Kingdom
The relevant deadline is the end of the 4 months beginning with the day on which the Authority receives the application; but this is subject to any extension under subsection (3).
If, before the deadline mentioned in subsection (2) (or before that deadline as previously extended under this subsection), the Authority asks the applicant or a relevant producer or supplier for information under section 10B(4) or (5), the relevant deadline is the end of the 4 months beginning with the day on which the last of that information is received.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
The Authority must publish its decision to certify or to refuse to certify the applicant, together with the reasons for it, in such manner as it considers appropriate.
Annotations
Textual amendments
- F1
Ss. 10A-10O and cross-heading inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 5
- F2
Word in s. 10D(1) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 46(2)(a) (with reg. 46(6)(7)) (as amended by S.I. 2020/1016, regs. 1(2), 3(17)); 2020 c. 1, Sch. 5 para. 1(1)
- F3
Word in s. 10D(1) substituted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 46(2)(b) (with reg. 46(6)(7)) (as amended by S.I. 2020/1016, regs. 1(2), 3(17)); 2020 c. 1, Sch. 5 para. 1(1)
- F4
Word in s. 10D(4) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 46(3)(a) (with reg. 46(6)(7)) (as amended by S.I. 2020/1016, regs. 1(2), 3(17)); 2020 c. 1, Sch. 5 para. 1(1)
- F5
Word in s. 10D(4)(a) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 46(3)(b) (with reg. 46(6)(7)) (as amended by S.I. 2020/1016, regs. 1(2), 3(17)); 2020 c. 1, Sch. 5 para. 1(1)
- F6
S. 10D(4)(c) and word omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 46(3)(c) (with reg. 46(6)(7)) (as amended by S.I. 2020/1016, regs. 1(2), 3(17)); 2020 c. 1, Sch. 5 para. 1(1)
- F7
S. 10D(5)-(8) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 46(4) (with reg. 46(6)(7)) (as amended by S.I. 2020/1016, regs. 1(2), 3(17)); 2020 c. 1, Sch. 5 para. 1(1)
- F8
S. 10D(9) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 46(5) (with reg. 46(6)(7)); 2020 c. 1, Sch. 5 para. 1(1)
Notes on Part I
Modifications
- C1
Pt. I modified (5.10.2004) by Energy Act 2004 (c. 20), ss. 184(12), 185(13), 198(2); S.I. 2004/2575, art. 2(1), Sch. 1
- C2
Pt. I modified (S.) (30.11.2005) by The Electricity from Non-Fossil Fuel Sources (Scotland) Saving Arrangements Order 2005 (S.S.I. 2005/549), arts. 1(1), 9
- C3
Pt. 1 excluded (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 7(2) (with art. 26)
- C4
Pt. I (ss. 1-64) applied (1.10.2001) by S.I. 2001/3264, regs. 4(2), 5(2)
- C5
Pt. I (ss. 1-64) amended (E.W.) (27.10.2000) by S.I. 2000/2727, art. 10
Pt. I (ss. 1-64) amended (7.11.2000) by 2000 c. 27, s. 105(1)(a); S.I. 2000/2974, art. 2, Sch. (subject to transitional provisions in arts. 3-12)
Pt. I (ss. 1-64) amended (E.W.) (1.10.2001) by S.I. 2000/2727, art. 10 (as substituted (1.10.2001) by S.I. 2001/3268, art. 2(13))