Section 6G Section 6F: meaning of “commissioning period”F1

England, Wales and Scotland

(1)

For the purposes of section 6F(3), transmission over F2a transmission system (or anything forming part of it) takes place during a “commissioning period” if it takes place at any time—

(a)

before a completion notice is given in respect of the system, or

(b)

during the period of F327 months beginning with the day on which such a notice is given.

(2)

A “completion notice”, in relation to a transmission system, is a notice which—

(a)

is given to the Authority by the relevant co-ordination licence holder in accordance with the co-ordination licence, and

(b)

states that it would be possible to carry on an activity to which section 4(1)(b) applies by making available for use that system.

F4(3)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(4)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(5)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(F56)

In this section—

  • “co-ordination licence” means F6a licence which authorises a person to co-ordinate and direct the flow of electricity onto and over a transmission system by means of which the transmission of electricity takes place and the whole or part of which is at a place in Great Britain, in the territorial sea adjacent to Great Britain or in a Renewable Energy Zone;

  • “relevant co-ordination licence holder” means the holder of a co-ordination licence to whom a person has applied (in accordance with any provision made by that licence) for an offer of connection to and use of a transmission system for the purposes of which the tender exercise is held.

Annotations

Textual amendments

F1

Ss. 6F-6H inserted (E.W.S.) (18.2.2014) by Energy Act 2013 (c. 32), ss. 147(3), 156(2)

F2

Word in s. 6G(1) substituted (26.10.2023) by Energy Act 2023 (c. 52), s. 334(2)(i), Sch. 15 para. 6(2)

F3

Words in s. 6G(1)(b) substituted (18.2.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 28, 118(1)(o) (with s. 116)

F4

S. 6G(3)-(5) omitted (26.10.2023) by virtue of Energy Act 2023 (c. 52), s. 334(2)(i), Sch. 15 para. 6(3)

F5

S. 6G(6) substituted (26.10.2023) by Energy Act 2023 (c. 52), s. 334(2)(i), Sch. 15 para. 6(4)

F6

Words in s. 6G(6) substituted (1.10.2024) by The Energy Act 2023 (Consequential Amendments) Regulations 2024 (S.I. 2024/706), regs. 1(1), 3(6); S.I. 2024/957, reg. 2(a)

Notes on Part I

Modifications

C1

Pt. I modified (5.10.2004) by Energy Act 2004 (c. 20), ss. 184(12), 185(13), 198(2); S.I. 2004/2575, art. 2(1), Sch. 1

C2

Pt. I modified (S.) (30.11.2005) by The Electricity from Non-Fossil Fuel Sources (Scotland) Saving Arrangements Order 2005 (S.S.I. 2005/549), arts. 1(1), 9

C3

Pt. 1 excluded (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 7(2) (with art. 26)

C4

Pt. I (ss. 1-64) applied (1.10.2001) by S.I. 2001/3264, regs. 4(2), 5(2)

C5

Pt. I (ss. 1-64) amended (E.W.) (27.10.2000) by S.I. 2000/2727, art. 10

Pt. I (ss. 1-64) amended (7.11.2000) by 2000 c. 27, s. 105(1)(a); S.I. 2000/2974, art. 2, Sch. (subject to transitional provisions in arts. 3-12)

Pt. I (ss. 1-64) amended (E.W.) (1.10.2001) by S.I. 2000/2727, art. 10 (as substituted (1.10.2001) by S.I. 2001/3268, art. 2(13))