Article 7 Determining a supplier’s obligations and minimum requirementsF8
England, Wales and Scotland
Except where paragraph (6) or (7) applies, the Administrator must also determine for each phase a supplier's provisional solid wall minimum requirement.
For the purposes of paragraphs (1) and (2), the Administrator must—
in the case of a supplier which is not a group company during the phase to which a determination relates, make the determination in accordance with article 8;
in the case of a supplier which is a group company during the phase to which a determination relates, make the determination in accordance with article 9.
Except where paragraph (6) or (7) applies, a supplier’s—
home heating minimum requirement for phase 3 is—
where “H” is the home heating cost reduction obligation determined under paragraph (1) for the supplier in respect of phase 3; and
rural minimum requirement for phase 3 is—
where “C” is the carbon emissions reduction obligation determined under paragraph (1) for the supplier in respect of phase 3.
The Administrator must notify a supplier of its obligations in paragraph (1) and its provisional solid wall minimum requirement—
for phase 1 and 2, by no later than the last day of February prior to the commencement of the phase;
for phase 3, by no later than 28 days after the commencement date.
Where a supplier—
is not a group company; and
has notified under article 6 a supply of gas or electricity for the relevant notification period which does not exceed a qualifying supply,
each of the supplier's obligations in paragraph (1) F6, the requirement in paragraph (2) and the requirements in paragraph (4) for a phase is zero.
Where a supplier—
is a group company; and
has notified under article 6 a supply of gas or electricity for the group for the relevant notification period which does not exceed a qualifying supply,
each of the supplier's obligations in paragraph (1) F7, the requirement in paragraph (2) and the requirements in paragraph (4) for a phase is zero.
A supplier is a group company during a phase where it is a member of a group with another supplier at the end of 31st December immediately before the commencement of that phase.
Annotations
Textual amendments
- F1
Words in art. 7(1) omitted (29.3.2017) by virtue of The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(2)(a)
- F2
Words in art. 7(1)(a) inserted (29.3.2017) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(2)(b)
- F3
Words in art. 7(1)(b) inserted (29.3.2017) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(2)(c)
- F4
Words in art. 7(1)(c) inserted (29.3.2017) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(2)(d)
- F5
Art. 7(4)(5) substituted (29.3.2017) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(3)
- F6
Words in art. 7(6) substituted (29.3.2017) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(4)
- F7
Words in art. 7(7) substituted (29.3.2017) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(5)
- F8
Words in art. 7 heading substituted (29.3.2017) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2017 (S.I. 2017/490), arts. 1(1), 7(1)