Article 23 Additional requirements to be met by heating control measuresI1
England, Wales and Scotland
A heating control measure meets the requirements of this article if it—
is installed at the same domestic premises where an ECO4A qualifying action that is an only or first insulation measure within the meaning of article 22(1)(c)(i) (“the related insulation measure”);
is completed—
on the same day as, or not more than three months after, the day on which the related insulation measure is completed; and
after the pre-installation energy efficiency assessment is performed; and
is promoted by the same participant who promoted the related insulation measure.
Annotations
Textual amendments
- F1
Art. 23(a) substituted (1.8.2025) by The Electricity and Gas (Energy Company Obligation) (Amendment) Order 2025 (S.I. 2025/941), arts. 1(2), 13(1)(b) (with art. 13(2))
Commencement
- I1
Art. 23 in force at 25.7.2023, see art. 1(2)