Regulation 11 Fees payable on applications for consent
Subject to paragraph (2), the fee to be paid to the Secretary of State upon application being made for a consent under section 36 or section 37 shall be as specified in the Table below.
TABLE
| Subject matter of application for consent | Fee |
|---|---|
| Overhead line | £50.00 |
| Generating station | |
1 Construction or construction and operation of non-nuclear station of megawatt capacity — | |
(a) not exceeding 200 | £5000.00 |
(b) exceeding 200 but not exceeding 500 | £12000.00 |
(c) exceeding 500 | £20000.00 |
2 Construction or construction and operation of nuclear station of megawatt capacity — | |
(a) not exceeding 200 | £10000.00 |
(b) exceeding 200 but not exceeding 500 | £24000.00 |
(c) exceeding 500 | £40000.00 |
3 Extension or extension and operation of non-nuclear station resulting in increase in megawatt capacity — | |
(a) not exceeding 200 | £5000.00 |
(b) exceeding 200 but not exceeding 500 | £12000.00 |
(c) exceeding 500 | £20000.00 |
4 Extension or extension and operation of nuclear station resulting in increase in megawatt capacity — | |
(a) not exceeding 200 | £10000.00 |
(b) exceeding 200 but not exceeding 500 | £24000.00 |
(c) exceeding 500 | £40000.00 |
5 Extension of station by retrofitting of emission control equipment | £5000.00 |
6 Any other extension of station | £1000.00 |
7 Operation only or charge to manner of operation of station | £1000.00 |
Where the subject matter of an application for a consent under section 36 is two or more of the matters specified under heads 3 to 7 in the Table above, the fee to be paid shall be the higher or highest of the relevant fees there specified.