Paragraph 2 F1
An outline statement of the business proposals, for the business of the applicant to which the application relates, for the next 5 years which includes—
particulars of the person or persons from whom, and the points at which, the applicant expects to receive the electricity which he will distribute; particulars of distribution of the electricity; particulars of the expected points of off-take, and quantities;
interconnections to other distribution systems and/or transmission systems;
proposed metering arrangements;
schedule of generating plant owned by the applicant including—
pumped storage; and
clutched gas turbine generators/synchronous compensators;
forecast annual maximum demands in his distribution system (GW) and energy (GWh) to be distributed;
summary large scale map, together with detailed maps providing information on areas where activities are concentrated as necessary;
a single line diagram of the distribution system showing all distribution voltage levels and distinguishing from overhead lines and electric lines which are or will be placed underground;
annual forecasts of costs, sales and revenues and project financing, stating the assumptions underlying the figures provided; and
details of the arrangements that are in place, or will be put in place, for managing the interfaces between the system to which the application relates and—
other distribution systems;
transmission systems;
the transmission system operator; and
any persons who are, or will be at any future point, connected to the system to which the application relates.
Annotations
Textual amendments
- F1
Sch. 6 inserted (15.4.2011) by The Gas and Electricity (Internal Markets) Regulations (Northern Ireland) 2011 (S.R. 2011/155), regs. 1, 33(g), Sch. 2