Explanatory note
England, Wales and Scotland
(This note is not part of the Regulations)
These Regulations set out the information, and other documents that are required to be submitted with applications for generation, transmission, distribution, supply and interconnector licences (and for modifications of an area of transmission licences and extensions, or restrictions of supply and distribution licences) under the Electricity Act 1989, as amended by the Utilities Act 2000 and the Energy Act 2004. They specify the form and manner of such applications. These Regulations also set out the manner in which notices of applications are to be published.
These Regulations come into force on 5th July 2019.
Regulation 1 provides for the citation, commencement and revokes the previous Regulations.
Regulation 2 makes transitional provisions for applications made but not determined before the Regulations come into force.
Regulation 3 provides for general interpretation.
Regulation 4 deals with the manner of applications.
Regulation 5 concerns the form of applications, and incorporates the Schedule that specifies their form, and the information and documents to accompany them.
Regulation 6 specifies the additional information and documents to accompany applications.
Regulation 7 specifies the fees payable in respect of applications. The fees for licence applications have increased by the following amounts:
| Description of application | Previous Fee payable £ | New Fee payable £ |
|---|---|---|
| Supply | ||
| Application for a licence to supply domestic and non-domestic premises | 450 | 2,150 |
| Application for a licence to supply non-domestic premises only | 450 | 1,800 |
| Application for any extension | 450 | 1,600 |
| Application for any restriction | 450 | 550 |
| Generation | ||
| Licence application | 500 | 550 |
| Distribution | ||
| Application for a licence | 1,400 | 3,200 |
| Application for extension or restriction | 150 | 800 |
| Transmission | ||
| Application for a licence | 500 | 3,200 |
| Application for the modification of an area | 250 | 800 |
| Interconnector | ||
| Application for a licence | 1,050 | 1,050 |
Regulation 8 provides for the notice period and publication requirements for applications. It requires applicants to request that the notice of the application is published on the Ofgem website or to publish it on their own website. If the application is for a restriction (including a modification of an area of a transmission licence to restrict that area) the applicant must also publish the notice in local newspapers.