Regulation 15 General eligibility criteria
The Delivery Body must not prequalify a CMU for a capacity auction unless it meets the general eligibility criteria.
The general eligibility criteria for a CMU are the conditions specified in paragraphs (3) to (5).
The first condition is that the CMU is in Great Britain or the offshore area.
The second condition is—
in the case of a generating CMU or an interconnector CMU, that the connection capacity of the CMU is equal to or greater than F21MW (the “minimum capacity threshold”); or
in the case of a demand side response CMU, that the DSR capacity of the CMU is equal to or greater than the minimum capacity threshold.
Annotations
Textual amendments
- F1
Reg. 15(4) substituted (24.3.2015) by The Electricity Capacity (Amendment) Regulations 2015 (S.I. 2015/875), reg. 1(2), Sch. 1 para. 14
- F2
Word in reg. 15(4)(a) substituted (4.7.2020) by The Electricity Capacity (Amendment etc.) (Coronavirus) Regulations 2020 (S.I. 2020/697), reg. 1(2), Sch. 1 para. 5
- F3
Word in reg. 15(5) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 47
- F4
Words in reg. 15(5) substituted (27.7.2021) by The Electricity Capacity (Amendment) Regulations 2021 (S.I. 2021/901), reg. 1(2), Sch. para. 1