Paragraph 3 Capacity payments: calculations to be made annually for each capacity committed CMU
The Settlement Body must, by no later than 3 months before the commencement of a delivery year (“year X”), calculate in respect of each capacity committed CMU (“CMU i”)—
the total amount in pounds of the capacity payments which, subject to regulation 40(5) and (6) and to regulations 49 to 51, are payable in respect of F1COix (“”); and
in respect of each month of year X (“month M”), the amount in pounds of the capacity payment which, subject to those regulations, is payable in respect of CMU i for that month (“”).
ACPyx (for any value y) must be calculated in accordance with the formula—
.
MCPim must be calculated in accordance with the formula—
.
For the purpose of sub-paragraph (3) tACPN is the amount ,
where—
“tICOiN” is any obligation, being the whole or part of the capacity obligation COzx, that has been transferred so as to—
- (a)
apply to CMU i for all or part of month M, or
- (b)
cease to apply to CMU i for all or part of month M (in which case tACPN is to be expressed as a negative number);
- (a)
“DTmN” means the number of days in month M for which that capacity obligation has been transferred;
“Dm” means the total number of days in month M.
If the relevant capacity auction was a T-4 auction, is to be calculated in accordance with the formula—
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
In this paragraph—
F7“CCPy” means the capacity cleared price for COyx, as recorded on the capacity market register
F8...
“” means the average of the monthly values of CPI for the months of the base period F9referred to in regulation 11 for the relevant capacity auction;
“” means the average of the monthly values of CPI for the months of the winter ending on the 30th April preceding the start of year X;
“relevant capacity auction” means the capacity auction in which F10COyx was awarded;
F11...
Annotations
Textual amendments
- F1
Words in Sch. 1 para. 3(1)(a) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(1) (with reg. 1(4))
- F2
Sch. 1 para. 3(2)-(3A) substituted for Sch. 1 para. 3(2)(3) (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(2) (with reg. 1(4))
- F3
Word in Sch. 1 para. 3(4) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(3) (with reg. 1(4))
- F4
Words in Sch. 1 para. 3(4) substituted (23.7.2025) by The Electricity Capacity (Amendment) (No. 2) Regulations 2025 (S.I. 2025/917), reg. 1(2), Sch. para. 18(a)(i)
- F5
Sch. 1 para. 3(5)(6): the subscript “y” substituted for the subscript “i” wherever it occurs (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(4) (with reg. 1(4))
- F6
Sch. 1 para. 3(6) omitted (23.7.2025) by virtue of The Electricity Capacity (Amendment) (No. 2) Regulations 2025 (S.I. 2025/917), reg. 1(2), Sch. para. 18(a)(ii)
- F7
Words in Sch. 1 para. 3(7) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(5)(a) (with reg. 1(4))
- F8
Words in Sch. 1 para. 3(7) omitted (14.7.2016) by virtue of The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(5)(b) (with reg. 1(4))
- F9
Words in Sch. 1 para. 3(7) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(5)(c) (with reg. 1(4))
- F10
Word in Sch. 1 para. 3(7) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(5)(d) (with reg. 1(4))
- F11
Words in Sch. 1 para. 3(7) omitted (14.7.2016) by virtue of The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 32(5)(e) (with reg. 1(4))