Paragraph 7 Over-delivery payments

(1)

The Settlement Body must, after the end of each delivery year (“year X”), determine for each relevant CMU (“CMU i”)—

(a)

the over-delivery rate in £/MWh applying to CMU i in respect of F1each relevant settlement period in year X (“ODRij”);

(b)

the amount in pounds of the over-delivery payment applying to CMU i in respect of each such settlement period in which CMU i over-delivered (“ODPij”); and

(c)

the amount in pounds of the total over-delivery payment applying to CMU i in respect of year X (“TODPix”).

(2)

F2Subject to sub-paragraph (2A), F3ODRij must be calculated in accordance with the F4formula—

ODRix=min(PRix,TPRxTODVx).
F5(2A)

For the purposes of the calculation in paragraph (2), where the over-delivery payment is to be made to a qualified person who is not a capacity provider in settlement period j, the value of PRij is deemed to be equal to the penalty rate applying to a capacity obligation awarded in the T-4 auction for year X and calculated in accordance with paragraph 5.

(3)

ODPijmust be calculated in accordance with the F6formula—

ODPij=ODRix×(AEij−ALFCOij).
(4)

TODPixmust be calculated as the sum of ODPij for all the relevant settlement periods in year X in which CMU i over-delivered.

(5)

For the purposes of this paragraph—

  • “over-delivered” is to be interpreted in accordance with regulation 42(2);

  • F7“PRij” means the penalty rate in pounds per MWh applying to CMU i in respect of settlement period j, as calculated in accordance with paragraph 5

  • F8“qualified person” has the meaning given in regulation 42(2);

  • a “relevant CMU” means a capacity committed CMU in respect of which AEij is greater than ALFCOij in one or more relevant settlement periods in year X;

  • “TODVx” means the aggregate in MWh of the total amounts over-delivered in year X by all relevant CMUs;

  • “TPRx” means the total amount of capacity market penalty charge payments received by the Settlement Body in respect of year X.

Annotations

Textual amendments

F1

Words in Sch. 1 para. 7(1)(a) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(1) (with reg. 1(4))

F2

Words in Sch. 1 para. 7(2) inserted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(3)(a) (with reg. 1(4))

F3

Sch. 1 para. 7(2): “ODRij” substituted for “ODRix” (wherever it occurs) (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(2) (with reg. 1(4))

F4

Sch. 1 para. 7(2): formula amended by the substitution of “PRij” for “PRix” (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(3)(b) (with reg. 1(4))

F5

Sch. 1 para. 7(2A) inserted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(4) (with reg. 1(4))

F6

Sch. 1 para. 7(3): “ODRij” substituted for “ODRix” (wherever it occurs) (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(2) (with reg. 1(4))

F7

Words in Sch. 1 para. 7(5) substituted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(5)(a) (with reg. 1(4))

F8

Words in Sch. 1 para. 7(5) inserted (14.7.2016) by The Electricity Capacity (Amendment) Regulations 2016 (S.I. 2016/742), reg. 1(2), Sch. 1 para. 36(5)(b) (with reg. 1(4))