OpenLegislation

Regulation 4 Forecast of relevant demand and CM EII excluded electricityF5I1

England, Wales and Scotland

(1)

Paragraph (2) applies to a person (“S”) who, on the 1st June before the start of a capacity year (“year X”), is an electricity supplier.

(2)

S must, by no later than the 1st June before the start of year X—

(a)

forecast its total F1relevant demand during periods of high demand in year X; F2...

F3(aa)

forecast the amount of CM EII excluded electricity that it will supply through meters in respect of which an EII certificate is in force during periods of high demand in year X; and

(b)

provide the F4forecasts to the Settlement Body.

Annotations

Textual amendments

F1

Words in reg. 4(2)(a) substituted (1.4.2024) by The Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024 (S.I. 2024/434), regs. 1(2), 9(b)(i)

F2

Word in reg. 4(2)(a) omitted (1.4.2024) by virtue of The Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024 (S.I. 2024/434), regs. 1(2), 9(b)(ii)

F3

Reg. 4(2)(aa) inserted (1.4.2024) by The Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024 (S.I. 2024/434), regs. 1(2), 9(b)(iii)

F4

Word in reg. 4(b) substituted (1.4.2024) by The Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024 (S.I. 2024/434), regs. 1(2), 9(c)

F5

Words in reg. 4 heading substituted (1.4.2024) by The Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024 (S.I. 2024/434), regs. 1(2), 9(a)

Commencement

I1

Reg. 4 in force at 18.12.2014, see reg. 1(2)