Paragraph 2 Capacity market supplier charge: provisional annual calculationsI1

England, Wales and Scotland

(1)

The Settlement Body must, by no later than three months before the start of a delivery year (“year X”), for each electricity supplier (“S”) calculate—

(a)

S’s provisional share of capacity market supplier charges in respect of year X (“PSCsx”);

(b)

S’s provisional capacity market supplier charge in respect of year X (“PACMSCsx”);

(c)

S’s provisional monthly capacity market supplier charge in respect of each month of year X (“PMCMSCsm”).

(2)

PSCsx must be calculated in accordance with the formula—

PSCsx=FSSPDsx∑sFSSPDsx.
(3)

PACMSCsx must be calculated in accordance with the formula—

PACMSCsx=∑iACPix×PSCsx.
(4)

PMCMSCsm must be calculated in accordance with the formula—

PMCMSCsm=PACMSCsx×WFmx.
(5)

In this paragraph—

  • “∑iACPix” means the sum of ACPix (the total amount of capacity payments payable in respect of a capacity committed CMU), as calculated under paragraph 3 of Schedule 1 to the Principal Regulations, for all capacity committed CMUs in respect of year X; and

  • F1“A black letter with a white backgroundDescription automatically generated” means the amount of the relevant demand forecast by S for year X under regulation 4(2)(a) and given to the Settlement Body under regulation 4(2)(b) less the CM EII excluded electricity forecast by S for year X under regulation 4(2)(aa) and given to the Settlement Body under regulation 4(2)(b).

Annotations

Textual amendments

F1

Words in Sch. 1 para. 2(5) substituted (1.4.2024) by The Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024 (S.I. 2024/434), regs. 1(2), 12(a)

Commencement

I1

Sch. 1 para. 2 in force at 18.12.2014, see reg. 1(2)