Regulation 11 Entry conditions in respect of qualifying projectsI1
England, Wales and Scotland
In respect of a qualifying project, the Authority must, at a time determined by the Authority, notify the developer of—
the information that the Authority will require in order to be satisfied—
in the case of a request for a generator build tender exercise, that the entry conditions specified in paragraph 2 of Schedule 2 have been met in respect of that particular qualifying project; or
in the case of a request for an OFTO build tender exercise, that the entry conditions specified in paragraph 1 of Schedule 2 have been met in respect of that particular qualifying project; and
the date by which each of the entry conditions specified in paragraph 1 or 2 of Schedule 2, as the case may be, must be met by the developer in respect of that qualifying project.
The Authority may require the developer to provide any other information it considers necessary in order to satisfy itself that the entry conditions specified in paragraph 1 or 2 of Schedule 2, as the case may be, have been met.
Where the Authority is satisfied that the entry conditions specified in paragraph 1 or 2 of Schedule 2, as the case may be, have been met in accordance with paragraph (1), it must give notice to that effect to the developer.