Regulation 11 Provision of information to subsequent contributorI1
England, Wales and Scotland
(1)
A subsequent contributor may request information from the relevant electricity distributor about—
(a)
the amount of the net first connection expenses (or, where regulation 10 applies, the relevant electricity distributor’s estimate of that amount);
(b)
the date on which the first connection was made; and
(c)
the total amount previously paid in respect of first connection expenses by—
(i)
the initial contributor; or
(ii)
persons previously required to make payments in respect of first connection expenses.
(2)
The relevant electricity distributor must, in so far as it holds the information, provide any information reasonably requested under paragraph (1) as soon as reasonably practicable.