Prescribed periods and prescribed sums applicable to all electricity distributors Prescribed periods and prescribed sums applicable to all electricity distributors
England, Wales and Scotland
F1(1) Regulation | (2) Prescribed period | (3) Prescribed sum | (4) Payment Date |
|---|---|---|---|
| 4(2) | 10 working days | £75 | the working day on which the budget estimate should have been dispatched |
| 4(3) | 20 working days | £75 | the working day on which the budget estimate should have been dispatched |
| 5(2) | 5 working days | £20 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 5(3) | 15 working days | £20 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 6(2) | 25 working days | £75 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 6(3) | 35 working days | £160 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 6(4) | 65 working days | £235 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 7(3) | not applicable | £395 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
| 7(4) | not applicable | £785 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
| 8(2) | 7 working days | £20 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 8(3) | the agreed date | £40 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(2) | 7 working days | £75 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 9(3) | 10 working days | £160 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 9(4) | 15 working days | £235 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 9(5) | the agreed date | £30 for each working day after the agreed date up to and including the day on which the works at the premises are commenced | the working day on which the works at the premises are commenced |
| 9(6) | the agreed date | £160 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(7) | the agreed date | £235 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(8) | the agreed date | £315 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(9) | the agreed date | £160 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
| 9(10) | the agreed date | £235 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
| 9(11) | the agreed date | £315 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
| 10(2) | 2 hours | £75 | the working day after the day on which the emergency attendance should have taken place |
| 10(3) | 2 calendar days | £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 10(4) | 10 working days | £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 10(5) | 20 working days | £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 10(6) | 25 working days | £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 11(2) | 25 working days | £20 for each working day after the end of the prescribed period up to and including the day the quotation is dispatched | the working day on which the quotation is dispatched |
| 12(2) | the agreed date | £20 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 12(3) | 35 working days | £20 for each working day after the end of the prescribed period up to and including the day on which the works are completed | the working day on which the works are completed |
| 14(1) | 10 working days | £75 | not applicable |
Annotations
Textual amendments
- F1
Sch. 1 Table substituted (1.10.2023) by The Electricity (Standards of Performance) (Amendment) Regulations 2023 (S.I. 2023/887), regs. 1(4), 3(4)