The Electricity (Exemption from the Requirement for a Generation Licence) (Frodsham) (England and Wales) Order 2015
S.I. 2015/1409 · Made 23 June 2015
Electricity, England And Wales
Made 23rd June 2015
Laid before Parliament 25th June 2015
Coming into force 25th July 2015
The Secretary of State makes the following Order in exercise of the powers conferred by section 5 of the Electricity Act 1989f1.
The Secretary of State has given notice of the proposal to make this Order in accordance with section 5(2) and (3) of that Act. No representations in respect of the proposal have been made.
Annotations to the whole text
Footnotes
- f1
-
1989 c.29. Section 5 was substituted by section 29 of the Utilities Act 2000 (c.27).
Contents
- 1Citation and commencement
- 2Interpretation
- 3Exemption from section 4(1)(a) of the Act
- Signature
- Explanatory note
1Citation and commencement
This Order may be cited as the Electricity (Exemption from the Requirement for a Generation Licence) (Frodsham) (England and Wales) Order 2015 and comes into force on 25th July 2015.
2Interpretation
In this Order—
-
“the Act” means the Electricity Act 1989;
-
“the company” means Frodsham Wind Farm Limited, a company registered in England and Wales with company number 07075301;
-
“the generating station” means the Frodsham onshore wind farm, an electricity generating station located at Ordnance Survey map reference SJ489780, near Frodsham, Cheshire;
-
“the total system in England and Wales” means—
- (a)
the transmission system of the holder of a licence under section 6(1)(b) of the Act; and
- (b)
all distribution systems,
in each case, to the extent located in England and Wales.
- (a)
3Exemption from section 4(1)(a) of the Act
Subject to paragraph (2), the company is granted exemption from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) in respect of the generating station.
The exemption granted in paragraph (1) is subject to compliance with the following conditions—
that the generating station is connected to the total system in England and Wales;
that, except in circumstances outside the reasonable control of the company, the generating station does not export more than 100 megawatts of electrical power to the total system in England and Wales; and
that the company does not hold a licence under section 6(1)(a) of the Act.
Signature
Andrea Leadsom
Minister of State
Department of Energy and Climate Change
23rd June 2015
Explanatory note
(This note is not part of the Order)
This Order grants exemption from the requirements of section 4(1)(a) of the Electricity Act 1989 (which prohibits the generation of electricity for supply to any premises without a licence) to Frodsham Wind Farm Limited in relation to the Frodsham onshore wind farm, an electricity generating station located at Ordnance Survey map reference SJ489780, near Frodsham, Cheshire.
A regulatory impact assessment in respect of exemptions from the requirements of section 4(1)(a) of the Electricity Act 1989 was prepared in 2001 and can be obtained from the Department of Energy and Climate Change, Energy Markets Unit, 4th Floor, 3 Whitehall Place, London, SW1A 2AW. Copies have been placed in the libraries of both Houses of Parliament.