OpenLegislation

The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Seagreen) (Scotland) Order 2024

S.I. 2024/700 · Made 23 May 2024 · Extends to England, Wales and Scotland

Up to date with all changes known to legislation.gov.uk, revised to 8 February 2025.

ELECTRICITY, SCOTLAND

Made 23rd May 2024

Laid before Parliament 24th May 2024

Coming into force 20th June 2024

The Secretary of State makes this Order in exercise of the powers conferred by section 5(1) of the Electricity Act 1989f1.

The Secretary of State has given notice of the proposal to make this Order in accordance with section 5(2) and (3) of that Act and has consulted with the Scottish Ministersf2, and has considered any representations made.

Annotations to the whole text

Footnotes

f1

1989 c. 29; section 5 was substituted by section 29 of the Utilities Act 2000 (c. 27), and relevant amendments were made by S.I. 2012/2400, 2014/631 and 2022/34.

f2

Under article 4 of, and Schedule 3 to, the Scotland Act 1998 (Transfer of Functions to the Scottish Ministers etc.) Order 1999 (S.I. 1999/1750), functions under section 5(1) of the Electricity Act 1989 are, in so far as they are exercisable in or as regards Scotland, only exercisable after consultation with the Scottish Ministers.

Contents

  1. 1Citation, commencement, extent and application
  2. 2Exemption from section 4(1)(b) of the Electricity Act 1989
  3. Signature
  4. Explanatory note

1Citation, commencement, extent and applicationI1

(1)

This Order may be cited as the Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Seagreen) (Scotland) Order 2024 and comes into force on 20th June 2024.

(2)

This Order extends to England and Wales and Scotland.

(3)

This Order applies in relation to Scotland only.

2Exemption from section 4(1)(b) of the Electricity Act 1989I1

(1)

The Secretary of State grants exemption from section 4(1)(b) of the Actf1 (prohibition on unlicensed transmission of electricity for supply) to Seagreen Wind Energy Limited in respect of transmissionf2 taking place over the transmission systemf3 connected to the Seagreen Offshore Wind Farm.

(2)

The exemption in paragraph (1) of this article applies for the period beginning with 20th June 2024 and ending with the earlier of—

(a)

the day after the day on which the transmission system connected to Seagreen Offshore Wind Farm is transferred to a successful bidderf4;

(b)

F131st March 2025.

(3)

In this article—

  • “the Act” means the Electricity Act 1989;

  • “Seagreen Offshore Wind Farm” means the generating station located approximately 27 kilometres off the coast of Angus, in the Northeast of Scotland, with its central point being approximately Latitude 56°35′17″N and Longitude 1°44′28″W;

  • “Seagreen Wind Energy Limited” means Seagreen Wind Energy Limited, a company registered in England and Wales with company number 06873902.

Signature

Andrew Bowie

Minister of State

Department for Energy Security and Net Zero

23rd May 2024

Explanatory note

(This note is not part of the Order)

This Order grants exemption from the requirement to hold an electricity transmission licence.

Section 4(1)(b) of the Electricity Act 1989 (c. 29) prohibits the transmission of electricity for supply without a licence. The Secretary of State, exercising the powers under section 5(1) of that Act, grants a time-limited exemption from the requirement to hold a transmission licence to Seagreen Wind Energy Limited in respect of the Seagreen Offshore Wind Farm.

A full impact assessment has not been produced for this instrument as it is a temporary measure. No, or no significant, impact on the private, voluntary or public sector is foreseen.