Regulation 12C Providing supply chain implementation statements or refusalsF1
The Secretary of State must as soon as practicable after a supply chain implementation application is received by the Secretary of State give a notice to the generator party applicant which includes—
a supply chain implementation statement; or
a refusal to provide a supply chain implementation statement and reasons for that refusal.
If the Secretary of State has not given a notice as set out in paragraph (1) within 60 working days of receiving a supply chain implementation application that satisfies the requirements set out in regulation 12B, the Secretary of State must provide a supply chain implementation statement to the generator party applicant.
Annotations
Textual amendments
- F1
Regs. 12A-12C inserted (25.6.2021) by The Contracts for Difference (Miscellaneous Amendments) Regulations 2021 (S.I. 2021/758), regs. 1(1), 10
Notes on Part 3
Textual amendments
- F1
Words in Pt. 3 heading omitted (E.W.S.) (13.6.2024) by virtue of The Contracts for Difference (Sustainable Industry Rewards) Regulations 2024 (S.I. 2024/710), regs. 1(1), 54