Regulation 7 Provision of information by generators to the delivery bodyI1
United Kingdom
Paragraph (2) applies where—
by virtue of a counterparty notice, the delivery body has sought to obtain information from a CFD counterparty;
some or all of the information sought has not been provided; and
the delivery body reasonably believes that the information may be obtained from F1a generator party.
The delivery body may give a notice (“a generator notice”) to a F2generator party requiring the relevant generator to provide to the delivery body information which the delivery body reasonably believes that the relevant generator holds (or is entitled to obtain) and which the delivery body reasonably requires to comply with an advice notice.
A generator notice must set out—
the information required; and
the date by which the information is to be provided.
The information required by a generator notice may include information in relation to the capital costs and operational costs of the electricity generating station which is the subject of the CFD to which the F3generator party is a party.
A generator notice may be varied or withdrawn by notice by the delivery body to the F4generator party.
A F5generator party must comply with a generator notice which is given to it.
The requirement imposed under paragraph (6) is to be treated as a relevant requirement on the F6generator party as a regulated person for the purposes of section 25 of the Electricity Act 1989.
Where the “generator party” is an unincorporated association, “generator party” is to be read as “a member of the generator party unincorporated association that is a regulated person for the purposes of section 25 of the Electricity Act 1989.
Annotations
Textual amendments
- F1
Words in reg. 7(1)(c) substituted (15.3.2015) by The Electricity Market Reform (General) (Amendment) Regulations 2015 (S.I. 2015/718), regs. 1, 2(4)(a)
- F2
Words in reg. 7(2) substituted (15.3.2015) by The Electricity Market Reform (General) (Amendment) Regulations 2015 (S.I. 2015/718), regs. 1, 2(4)(b)
- F3
Words in reg. 7(4) substituted (15.3.2015) by The Electricity Market Reform (General) (Amendment) Regulations 2015 (S.I. 2015/718), regs. 1, 2(4)(b)
- F4
Words in reg. 7(5) substituted (15.3.2015) by The Electricity Market Reform (General) (Amendment) Regulations 2015 (S.I. 2015/718), regs. 1, 2(4)(b)
- F5
Words in reg. 7(6) substituted (15.3.2015) by The Electricity Market Reform (General) (Amendment) Regulations 2015 (S.I. 2015/718), regs. 1, 2(4)(b)
- F6
Words in reg. 7(7) substituted (15.3.2015) by The Electricity Market Reform (General) (Amendment) Regulations 2015 (S.I. 2015/718), regs. 1, 2(4)(b)
- F7
Reg. 7(8) inserted (20.7.2016) by The Contracts for Difference (Miscellaneous Amendments) Regulations 2016 (S.I. 2016/784), regs. 1(1), 25
Commencement
- I1
Reg. 7 in force at 1.8.2014, see reg. 1