(1)

Where a customer has not, within the requisite period, paid all charges due from him to an electricity supplier in respect of the supply of electricity to any premises or the provision of an electricity meter, the supplier may, after the expiration of not less than 2 working days notice of his intention—

(a)

cut off the supply to the premises or to any other premises occupied by the customer, by such means as he thinks fit; and

(b)

recover any expenses incurred in so doing from the customer.

(2)

The power of a supplier under sub-paragraph (1) shall also be exercisable at any time which, in relation to a customer, is after the effective date for the purposes of Article 343 of the Insolvency (Northern Ireland) Order 1989 (supplies of gas, water, electricity etc. to insolvent companies).

(3)

The power of a supplier conferred by sub-paragraph (1) shall not be exercisable as respects any amount which is genuinely in dispute; but there shall be disregarded for this purpose any dispute arising under Article 42 or regulations made under it.

(4)

In this paragraph the “requisite period” means—

(a)

in the case of premises which are wholly or mainly used for domestic purposes, the period of 20 working days after the making by the supplier of a demand in writing for payment of the charges due; and

(b)

in any other case, the period of 15 working days after the making of such a demand.

Annotations

Textual amendments

F1

Sch. 6 substituted (1.11.2007) by Electricity Regulations (Northern Ireland) 2007 (S.R. 2007/321), regs. 1(2), 5(2), Sch. 1 (with transitional provisions in Pt. IV)