OpenLegislation

Regulation 5 PublicationI1

England and Wales

(1)

Where an applicant has received a notice under regulation 4(6), the variation application must be published, and its publication advertised, in accordance with this regulation.

(2)

The applicant or, where paragraph (3) applies, the Welsh Ministers must publish on a website (the “application website”)—

(a)

a summary of the variation application;

(b)

the application;

(c)

a link to the relevant section 36 consent, any section 90 direction given on granting the relevant section 36 consent and any statement (in the form of a decision letter, decision notice or otherwise) given by the appropriate authority M1 under regulation 10(3) of the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2000 M2 or regulation 33 of the EIA Regulations on granting the relevant section 36 consent.

(3)

This paragraph applies where the Welsh Ministers notify the developer in writing that the Welsh Ministers will comply with the obligations in paragraph (2).

(4)

The applicant must serve a copy of the application on the relevant planning authority (if any).

(5)

The applicant must publish notice of the variation application—

(a)

in two successive weeks in one or more local newspapers which are likely to come to the attention of those likely to be affected by the proposed development;

(b)

in the London Gazette;

(c)

in Lloyd's List and in one or more F1newspapers circulating in Wales, England and Northern Ireland; and

(d)

if there are in circulation one or more appropriate fishing trade journals which are published at intervals not exceeding one month, in at least one such trade journal.

and serve a copy of the notice on the relevant planning authority (if any).

(6)

The notice required by paragraph (5) must—

(a)

not be published before the applicant has complied with paragraphs (2) and (4) or, where paragraph (3) applies, the Welsh Ministers have complied with paragraph (2) and the applicant has complied with paragraph (4);

(b)

state—

(i)

that a variation application has been made and that the applicant has received a notice under regulation 4(6);

(ii)

the address of the application website, and that further information about the application is to be found on the application website;

(iii)

the date, not less than four weeks after the date on which the last notice is to be published, by which any person other than a relevant planning authority must send objections to the proposed development, or other representations about the application, to the Welsh Ministers; and

(iv)

the address to which any such representations are to be sent; and

(c)

identify—

(i)

the applicant;

(ii)

the relevant section 36 consent;

(iii)

the generating station to which it relates; and

(iv)

a place which is reasonably accessible to those likely to be affected by the proposed development where copies of the variation application may be inspected.

Annotations

Textual amendments

F1

Words in reg. 5(5)(c) substituted (5.7.2019) by The Electricity (Offshore Generating Stations) (Miscellaneous Amendments) (Wales) Regulations 2019 (S.I. 2019/1017), regs. 1, 3(3)

Marginal citations

M1

See section 36C(6) of the 1989 Act for the meaning of “appropriate authority”.

M2

S.I. 2000/1927 which was amended by S.I. 2007/1977 and revoked by S.I. 2017/580 subject to the transitional provision as specified in regulation 42 of that instrument.

Commencement

I1

Reg. 5 in force at 1.4.2019, see reg. 1