Regulation 15 Screening decisions: general
The relevant authority must make a screening decision on the basis of the information provided by the developer, taking account, where relevant, of—
the criteria set out in Schedule 3;
the views (if any) of every local planning authority consulted.
If the relevant authority thinks that the development is likely to have significant effects on the environment, the relevant authority must make a screening decision that the development is EIA development.
The relevant authority must send the screening decision to the developer as soon as reasonably practicable after it is made.
If the screening decision is that the development is EIA development, the screening decision must state the main reasons for the decision by reference to the criteria set out in Schedule 3.
If the screening decision is that the development is not EIA development, the screening decision must state—
the main reasons for the decision by reference to the criteria set out in Schedule 3; and
any features of the development and measures envisaged to avoid or prevent what might otherwise be significant adverse effects on the environment.
Annotations
Textual amendments
- F1
Words in reg. 15(1)(b) substituted (31.12.2020) by The Pipe-lines, Petroleum, Electricity Works and Oil Stocking (Miscellaneous Amendments) (EU Exit) Regulations 2018 (S.I. 2018/1325), regs. 1(1), 10(3); 2020 c. 1, Sch. 5 para. 1(1)
- F2
Word in reg. 15(1)(b) substituted (27.2.2025) by The Retained EU Law (Revocation and Reform) Act 2023 (Consequential Amendments) Regulations 2025 (S.I. 2025/82), reg. 1(2), Sch. 13 para. 8(2)(b)