Regulation 5 Carbon capture and storage (CCS) notification
(1)
For the purposes of section 58 of the Act, the chief inspector must not consider a complete CCS system to be ready for use unless he has first received from the operator a notification (“a CCS notification”) in respect of the system.
(2)
A CCS notification must state—
(a)
each generating unit within the relevant fossil fuel plant to which the complete CCS system relates;
(b)
the installed generating capacity of all the generating units specified under sub-paragraph (a); and
(c)
the date on which the operator wishes the complete CCS system is to be considered ready for use.
(3)
A CCS notification must be submitted in such form and manner as the chief inspector may reasonably require.