Paragraph 32 I1
In sub-paragraph (1) of paragraph 111 (interpretation)—
omit the definitions of “correspondence”, “holder of a qualifying floating charge”, “market value”, “the purpose of administration” and “unable to pay its debts”;
after the definition of “administrator” (as amended by virtue of paragraph 4 of this Schedule) insert—
““appropriate value” means the best price which would be reasonably available on a sale which is consistent with the achievement of the objective of the energy administration;”
for the definition of “company” substitute—
““company”, “court” and “energy administration order” have the same meanings as in Chapter 3 of Part 3 of the Energy Act 2004;”
after the definition of “creditors' meeting” insert—
““energy administration application” means an application to the court for an energy administration order under Chapter 3 of Part 3 of the Energy Act 2004;
“GEMA” means the Gas and Electricity Markets Authority;”
after the definition of “hire purchase agreement” insert—
““objective”, in relation to an energy administration, is to be construed in accordance with section 155 of the Energy Act 2004;
“prescribed” means prescribed by energy administration rules within the meaning of Chapter 3 of Part 3 of the Energy Act 2004;”.
After sub-paragraph (3) of that paragraph insert—
“(4)For the purposes of this Schedule a reference to an energy administration order includes a reference to an appointment under paragraph 91 or 103.”
Annotations
Commencement
- I1
Sch. 20 para. 32 in force at 5.10.2004 by S.I. 2004/2575, art. 2(1), Sch. 1
Notes on Schedule 20
Modifications
- C1
Sch. 20 modified (1.10.2005) by Energy Administration Rules 2005 (S.I. 2005/2483), rules 1, 184 (with rules 3, 187)
- C2
Sch. 20 applied (with modifications) (18.12.2011) by Energy Act 2011 (c. 16), s. 96(1)-(4), 121(3)
- C3
Sch. 20 modified (7.6.2013) by The Energy Supply Company Administration Rules 2013 (S.I. 2013/1046), rules 1, 205(2)-(4) (with rules 3, 208)
- C4
Sch. 20 applied (with modifications) (23.7.2018) by Smart Meters Act 2018 (c. 14), ss. 4(1)-(4), 14(5)
- C5
Schs. 20, 21 modified (E.W.) (1.8.2020) by The Smart Meter Communication Licensee Administration (England and Wales) Rules 2020 (S.I. 2020/629), rules 1, 3(2)-(4) (with rule 4(1))
- C6
Sch. 20 applied (with modifications) (31.3.2022 for specified purposes, 1.6.2022 in so far as not already in force) by Nuclear Energy (Financing) Act 2022 (c. 15), ss. 33(1)-(5), 44(1)(c)(2)(c)
- C7
Sch. 20 power to apply (with modifications) conferred (26.10.2023) by Energy Act 2023 (c. 52), s. 334(2)(l), Sch. 18 para. 50
- C8
Sch. 20 applied (with modifications) (26.12.2023) by Energy Act 2023 (c. 52), ss. 44, 334(3)(a)