OpenLegislation

Paragraph 35 Protection of groundwater: monitoringF1

(1)

The monitoring of groundwater must be carried out in accordance with Table 12.

(2)

The parameters to be analysed in the samples taken must be derived from the expected composition of the leachate and the groundwater quality in the area.

(3)

In selecting the parameters for analysis, the mobility in the groundwater zone must be taken into account.

(4)

Parameters may include indicator parameters in order to ensure an early recognition of change in water quality.

(5)

The recommended parameters are pH, TOC, phenols, heavy metals, fluoride, As, oil/hydrocarbons.

Table 12

Operational phaseAfter-care phase
(1)

If there are fluctuating groundwater levels, the frequency must be increased.

(2)

The frequency must be based on the possibility for remedial action between two samplings if a trigger level is reached, i.e., the frequency must be determined on the basis of knowledge and the evaluation of the velocity of groundwater flow.

(3)

When a trigger level is reached (see paragraph 36), verification is necessary by repeating the sampling. When the level has been confirmed, a contingency plan set out in the landfill permit conditions must be followed.

Level of groundwaterEvery six monthsf1Every six months
Groundwater compositionSite-specific frequencySite-specific frequencyf2f3

Annotations

Textual amendments

F1

Sch. 13 inserted (1.11.2025) by The Environmental Authorisations (Scotland) Amendment Regulations 2025 (S.S.I. 2025/165), reg. 1(2), sch. 4 (with sch. 23)

Footnotes

f1

(1)

If there are fluctuating groundwater levels, the frequency must be increased.

f2

(2)

The frequency must be based on the possibility for remedial action between two samplings if a trigger level is reached, i.e., the frequency must be determined on the basis of knowledge and the evaluation of the velocity of groundwater flow.

f3

(3)

When a trigger level is reached (see paragraph 36), verification is necessary by repeating the sampling. When the level has been confirmed, a contingency plan set out in the landfill permit conditions must be followed.