OpenLegislation

Regulation 21 Review of decisions and consentsI1

England and Wales

Schedule 4 applies if, after the date of—

(a)

a decision that a project is not a significant project, or

(b)

a decision to grant consent for a project,

a site becomes a European site and Natural England considers that the carrying out or completion (within the meaning of “completed” in regulation 18(6)) of the project would be likely to have a significant effect on that site and would not be directly connected with or necessary for the management of the site.

Annotations

Commencement

I1

Reg. 21 in force at 10.10.2006, see reg. 1(2)