Regulation 20 Review of decisions and consentsI1
England and Wales
Schedule 4 applies if, after the date of—
(a)
a decision that a project is not a significant project, or
(b)
a decision to grant consent for a project,
the relevant land becomes a European site and the Welsh Ministers consider that the carrying out or completion (within the meaning of “completed” in regulation 17(6)) of the project would be likely to have a significant effect on that site and would not be directly connected with or necessary for the management of the site.
Annotations
Commencement
- I1
Reg. 20 in force at 16.5.2017, see reg. 1(3)