OpenLegislation

Paragraph 2 Interpretation

England and Wales

(1)

In this Schedule—

  • F1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • “large combustion plant” means a combustion plant with a total rated thermal input of 50 or more megawatts to which Chapter III of the Industrial Emissions Directive applies.

F2(2)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Annotations

Textual amendments

F1

Words in Sch. 15 para. 2(1) omitted (30.1.2018) by virtue of The Environmental Permitting (England and Wales) (Amendment) Regulations 2018 (S.I. 2018/110), regs. 1, 14

F2

Sch. 15 para. 2(2) omitted (31.12.2020) by virtue of The Environmental Permitting (England and Wales) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/39), regs. 1, 2(19)(a); 2020 c. 1, Sch. 5 para. 1(1)