Column 1Column 2
HLS capital works item Maximum percentage of cost
(a)

Installation of silt traps

60% of cost
(b)

Installation of wind pumps for maintenance of water levels

80% of cost
(c)

Improvement of droves

50% of cost
(d)

Construction of water penning structures

80% of cost
(e)

Use of native seed mix in relation to the reversion of arable land

100% of cost
(f)

Major preparatory work in relation to the re-creation of heathland

100% of cost
(g)

Installation of livestock handling facilities

60% of cost
(h)

Protection of historical and archaeological features

100% of cost
(i)

Restoration of historic farm buildings

80% of cost