OpenLegislation

Article 2 Definitions and interpretationF2

United Kingdom

Original text. Later amendments are not shown.

For the purposes of this Decision the following definitions apply:

  1. (1)

    ‘minimum start-up load for stable generation’ means the minimum load compatible with the steady operation of the generating combustion plant following start-up initiation after which the plant is able to safely and reliably deliver its output to a network, grid, heat accumulator or industrial site;

  2. (2)

    ‘minimum shut-down load for stable generation’ means the minimum load at which point the plant can no longer safely and reliably deliver its output to a network, grid, heat accumulator or industrial site and is considered to be shutting down.

  3. (3)

    F1For the purpose of this Decision a reference to a provision of a Directive is to be read as a reference to that provision in so far as it has been transposed into the law of any part of the United Kingdom.

Annotations

Textual amendments

F1

Art. 2(3) inserted (31.12.2020) by The Air Quality (Miscellaneous Amendment and Revocation of Retained Direct EU Legislation) (EU Exit) Regulations 2018 (S.I. 2018/1407), regs. 1, 8(2)(b); 2020 c. 1, Sch. 5 para. 1(1)

F2

Words in Art. 2 heading inserted (31.12.2020) by The Air Quality (Miscellaneous Amendment and Revocation of Retained Direct EU Legislation) (EU Exit) Regulations 2018 (S.I. 2018/1407), regs. 1, 8(2)(a); 2020 c. 1, Sch. 5 para. 1(1)