Division 4.2.3.6.3 Contingency arrangementsF1
United Kingdom
The infrastructure manager in conjunction with all the railway undertakings operating over his infrastructure, and neighbouring infrastructure managers as appropriate, must define, publish and make available appropriate contingency measures and assign responsibilities based on the requirement to reduce any negative impact as a result of degraded operation.
The planning requirements and the response to such events must be proportional to the nature and potential severity of the degradation.
These measures, which must as a minimum include plans for recovering the network to ‘ normal ’ status, may also address:
-
rolling stock failures (for example, those which could result in substantial traffic disruption, the procedures for rescuing failed trains),
-
infrastructure failures (for example, when there has been a failure of the electric power or the conditions under which trains may be diverted from the booked route),
-
extreme weather conditions.
The infrastructure manager must establish and keep updated contact information for key infrastructure manager and railway undertaking staff who may be contacted in the event of service disruption leading to degraded operation. This information must include contact details both during and outside office hours.
The railway undertaking must submit this information to the infrastructure manager and advise the infrastructure manager of any changes to these contact details.
The infrastructure manager must advise all the railway undertaking(s) of any changes to his details.