Division 1 INTRODUCTION
United Kingdom
The purpose of this document, Annex 2 to the Statutes, is to describe the overall cost estimates, the budget and the planned schedule for the ESS project. It is a high-level summary of the performance baseline established in spring 2014, based on the TDR and associated documents presented to the ESS Steering Committee in 2012 and in line with the technical and scientific scope summarised in Annex 1. All cost figures in this document are on the price basis of January 2013.