Division Budget Item: 6711
United Kingdom
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
|---|---|---|---|---|---|---|---|---|---|
| AT | Rural Development EAFRD (2014-2020) measures subject to IACS | 2015 | measure 214: implementation of an appropriate sanction system | FLAT RATE | 5,00 % | EUR | – 5 958,97 | 0,00 | – 5 958,97 |
| Rural Development EAFRD (2014-2020) measures subject to IACS | 2015 | measure 214 ‘Organic Farming’ — Adequate supervision procedure | EXTRAPOLATED | 0,21 % | EUR | – 101 920,89 | 0,00 | – 101 920,89 | |
| Total AT: | EUR | – 107 879,86 | 0,00 | – 107 879,86 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| BG | Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2010 | 5 % flat rate correction for deficiencies in OTSC, verification of public procurement, the reasonableness of costs and ineligible expenditure | FLAT RATE | 5,00 % | EUR | – 2 793 872,47 | – 2 793 872,47 | 0,00 |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2011 | 5 % flat rate correction for deficiencies in OTSC, verification of public procurement, the reasonableness of costs and ineligible expenditure | FLAT RATE | 5,00 % | EUR | – 1 074 263,6 | – 1 074 263,6 | 0,00 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2012 | 5 % flat rate correction for deficiencies in OTSC, verification of public procurement, the reasonableness of costs and ineligible expenditure | FLAT RATE | 5,00 % | EUR | – 780 941,24 | – 780 941,24 | 0,00 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | 5 % flat rate correction for deficiencies in OTSC, verification of public procurement, the reasonableness of costs and ineligible expenditure | FLAT RATE | 5,00 % | EUR | – 1 637 751,75 | 0,00 | – 1 637 751,75 | |
| Rural Development EAFRD Investment — public beneficiaries | 2014 | 5 % flat rate correction for deficiencies in OTSC, verification of public procurement, the reasonableness of costs and ineligible expenditure | FLAT RATE | 5,00 % | EUR | – 1 690 283,33 | 0,00 | – 1 690 283,33 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2010 | Adjustment due to national authorities withdrawing previous corrected amounts | ONE OFF | EUR | 259 643,71 | 0,00 | 259 643,71 | ||
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2011 | Adjustment due to national authorities withdrawing previous corrected amounts | ONE OFF | EUR | 107 839,98 | 0,00 | 107 839,98 | ||
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2012 | Adjustment due to national authorities withdrawing previous corrected amounts | ONE OFF | EUR | 51 063,74 | 0,00 | 51 063,74 | ||
| Cross Compliance | 2013 | Deficiencies in the scope, extent and quality of OTSC and reporting for SMR7 and 8, application of tolerances, CY2012 | FLAT RATE | 3,00 % | EUR | – 27 147,64 | 0,00 | – 27 147,64 | |
| Cross Compliance | 2014 | Deficiencies in the scope, extent and quality of OTSC and reporting for SMR7 and 8, application of tolerances, CY2013 | FLAT RATE | 6,00 % | EUR | – 105 957,72 | 0,00 | – 105 957,72 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2010 | Extrapolated 9 % correction-weaknesses concerning the reasonableness of costs and ineligible expenditure | EXTRAPOLATED | 9,00 % | EUR | – 4 183 858,87 | – 418 385,89 | – 3 765 472,98 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2011 | Extrapolated 9 % correction-weaknesses concerning the reasonableness of costs and ineligible expenditure | EXTRAPOLATED | 9,00 % | EUR | – 896 213,65 | – 89 621,36 | – 806 592,29 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2012 | Extrapolated 9 % correction-weaknesses concerning the reasonableness of costs and ineligible expenditure | EXTRAPOLATED | 9,00 % | EUR | – 556 147,52 | – 55 614,76 | – 500 532,76 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Extrapolated 9 % correction-weaknesses concerning the reasonableness of costs and ineligible expenditure | EXTRAPOLATED | 9,00 % | EUR | – 2 893 246,02 | 0,00 | – 2 893 246,02 | |
| Cross Compliance | 2015 | Failure to achieve the mandatory control rate for SMR7 and 8, weakness in the increase of the control rate, CY2014 | FLAT RATE | 10,00 % | EUR | – 350 314,96 | 0,00 | – 350 314,96 | |
| Total BG: | EUR | – 16 571 451,34 | – 5 212 699,32 | – 11 358 752,02 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| DE | Rural Development EAFRD Investment — public beneficiaries | 2014 | Financial errors in public procurements audited | ONE OFF | EUR | – 351 787,61 | – 349 181,08 | – 2 606,53 | |
| Rural Development EAFRD (2014-2020) Investment — public beneficiaries | 2015 | Financial errors in public procurements audited | ONE OFF | EUR | – 159 761,9 | 0,00 | – 159 761,9 | ||
| Certification | 2015 | Financial errors in the EAFRD population | ONE OFF | EUR | – 511 727,53 | 0,00 | – 511 727,53 | ||
| Total DE: | EUR | – 1 023 277,04 | – 349 181,08 | – 674 095,96 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| ES | Cross Compliance | 2013 | Deficiencies in the scope and quality of OTSC — Deficient reporting of OTSC — Late performance of OTSC — Deficient risk analysis — Pillar II — CY 2013 | FLAT RATE | 2,00 % | EUR | 2,40 | 0,00 | 2,40 |
| Cross Compliance | 2014 | Deficiencies in the scope and quality of OTSC — Deficient reporting of OTSC — Late performance of OTSC — Deficient risk analysis — Pillar II — CY 2013 | FLAT RATE | 2,00 % | EUR | – 2 272,97 | 0,00 | – 2 272,97 | |
| Cross Compliance | 2014 | Deficiencies in the scope and quality of OTSC — Deficient reporting of OTSC — Late performance of OTSC — Pillar II — CY 2014 | FLAT RATE | 2,00 % | EUR | 1,06 | 0,00 | 1,06 | |
| Cross Compliance | 2015 | Deficiencies in the scope and quality of OTSC — Deficient reporting of OTSC — Late performance of OTSC — Pillar II — CY 2014 | FLAT RATE | 2,00 % | EUR | – 2 493,06 | 0,00 | – 2 493,06 | |
| Cross Compliance | 2013 | Deficiencies in the scope and quality of OTSC — Late performance of OTSC — Deficient sampling of parcels for OTSC — Deficient risk analysis — Pillar II — CY 2012 | FLAT RATE | 2,00 % | EUR | – 180,81 | 0,00 | – 180,81 | |
| Certification | 2013 | Material error in EAFRD accounts | ONE OFF | EUR | – 903 456,8 | – 17 985,15 | – 885 471,65 | ||
| Total ES: | EUR | – 908 400,18 | – 17 985,15 | – 890 415,03 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| FR | Rural Development EAFRD Investment — private beneficiaries | 2014 | Deficiencies in the verification of the reasonableness of the costs and of the payment claims Measures 121 and 123 | FLAT RATE | 5,00 % | EUR | – 4 980 641,31 | – 41 685,4 | – 4 938 955,91 |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Deficiencies in the verification of the reasonableness of the costs and of the payment claims Measures 121 and 123 | FLAT RATE | 5,00 % | EUR | – 396 917,7 | 0,00 | – 396 917,7 | |
| Rural Development EAFRD (2014-2020) Investment — private beneficiaries | 2015 | Deficiencies in the verification of the reasonableness of the costs and of the payment claims of Measures 121 and 123 | FLAT RATE | 5,00 % | EUR | – 4 482 936,52 | 0,00 | – 4 482 936,52 | |
| Rural Development EAFRD (2014-2020) Investment — private beneficiaries | 2016 | Deficiencies in the verification of the reasonableness of the costs and of the payment claims of Measures 121 and 123 | FLAT RATE | 5,00 % | EUR | – 1 595 408,44 | 0,00 | – 1 595 408,44 | |
| Rural Development EAFRD (2014-2020) Investment — private beneficiaries | 2015 | Deficiency in the verification of reasonableness of the costs: correction with recurrence for Measures 121C4 and 123A | FLAT RATE | 10,00 % | EUR | – 3 184 129,2 | – 1 592 064,61 | – 1 592 064,59 | |
| Rural Development EAFRD (2014-2020) Investment — private beneficiaries | 2016 | Deficiency in the verification of reasonableness of the costs: correction with recurrence for Measures 121C4 and 123A | FLAT RATE | 10,00 % | EUR | – 1 279 291,51 | – 639 645,75 | – 639 645,76 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Deficiency in the verification of reasonableness of the costs: correction with recurrence for Measures 121C4 and 123A | FLAT RATE | 10,00 % | EUR | – 344 907,12 | – 171 577,47 | – 173 329,65 | |
| Rural Development EAFRD Investment — private beneficiaries | 2014 | Deficiency in the verification of reasonableness of the costs: correction with recurrence for Measures 121C4 and 123A | FLAT RATE | 10,00 % | EUR | – 2 802 935,54 | – 1 404 390,37 | – 1 398 545,17 | |
| Rural Development EAFRD Investment — public beneficiaries | 2014 | Exclusion of ineligible expenditure M321 | ONE OFF | EUR | – 68 062,01 | 0,00 | – 68 062,01 | ||
| Certification | 2012 | management weaknesses | ONE OFF | EUR | – 16 845 764,04 | 0,00 | – 16 845 764,04 | ||
| Certification | 2013 | management weaknesses in the FY2013 | ONE OFF | EUR | – 10 359 335,4 | 0,00 | – 10 359 335,4 | ||
| Total FR: | EUR | – 46 340 328,79 | – 3 849 363,6 | – 42 490 965,19 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| GB | Rural Development EAFRD Axis 2 (2007-2013, area related measures) | 2014 | measure 214 — FY2014: weaknesses in the control system for livestock density (both administrative and on the spot) | FLAT RATE | 5,00 % | EUR | – 538 979,08 | 0,00 | – 538 979,08 |
| Rural Development EAFRD (2014-2020) measures subject to IACS | 2015 | measure 214 — FY2015: weaknesses in the control system for livestock density (both administrative and on the spot) | FLAT RATE | 5,00 % | EUR | – 543 702,51 | 0,00 | – 543 702,51 | |
| Rural Development EAFRD Axis 2 (2007-2013, area related measures) | 2014 | measure 221 — FY2014: weaknesses in the check of eligibility criteria | ONE OFF | EUR | – 12 204,0 | 0,00 | – 12 204,0 | ||
| Rural Development EAFRD (2014-2020) forestry measures | 2015 | measure 221 — FY2015: weaknesses in the check of eligibility criteria | ONE OFF | EUR | – 12 204,0 | 0,00 | – 12 204,0 | ||
| Rural Development EAFRD LEADER | 2014 | One deficient key control and one absent ancillary control | FLAT RATE | 5,00 % | EUR | – 602 585,37 | 0,00 | – 602 585,37 | |
| Rural Development EAFRD LEADER | 2015 | One deficient key control and one absent ancillary control | FLAT RATE | 5,00 % | EUR | 4 026,71 | 0,00 | 4 026,71 | |
| Rural Development EAFRD LEADER | 2016 | One deficient key control and one absent ancillary control | FLAT RATE | 5,00 % | EUR | 368,09 | 0,00 | 368,09 | |
| Total GB: | EUR | – 1 705 280,16 | 0,00 | – 1 705 280,16 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| GR | Cross Compliance | 2013 | Weakness in risk analysis, MRFPP and SMR1, CY2012 | FLAT RATE | 2,00 % | EUR | – 229 711,85 | 0,00 | – 229 711,85 |
| Cross Compliance | 2014 | Weakness in risk analysis, MRFPP and SMR1, CY2012 | FLAT RATE | 2,00 % | EUR | – 57 428,76 | 0,00 | – 57 428,76 | |
| Total GR: | EUR | – 287 140,61 | 0,00 | – 287 140,61 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| IT | Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Deficiencies in key control: ‘Appropriate evaluation of the reasonableness of costs using a suitable evaluation system’related to the General costs | ONE OFF | EUR | – 26 409,49 | 0,00 | – 26 409,49 | |
| Rural Development EAFRD Investment — private beneficiaries | 2014 | Deficiencies in key control: ‘Appropriate evaluation of the reasonableness of costs using a suitable evaluation system’related to the General costs | ONE OFF | EUR | – 45 475,98 | 0,00 | – 45 475,98 | ||
| Rural Development EAFRD (2014-2020) Risk management | 2015 | Deficiencies in key control: ‘Appropriate evaluation of the reasonableness of costs using a suitable evaluation system’related to the General costs | ONE OFF | EUR | – 133 118,88 | 0,00 | – 133 118,88 | ||
| Cross Compliance | 2013 | Leniency of the sanctioning system in animal area, CY2012 | ONE OFF | EUR | – 7 112,87 | 0,00 | – 7 112,87 | ||
| Cross Compliance | 2015 | Limited access to veterinarian control reports, CY2014 | FLAT RATE | 2,00 % | EUR | – 175 426,91 | 0,00 | – 175 426,91 | |
| Cross Compliance | 2014 | No check for one GAEC and partial check of two SMRs, Farmer without animals, CY2013 | FLAT RATE | 2,00 % | EUR | – 39 153,87 | 0,00 | – 39 153,87 | |
| Cross Compliance | 2014 | Partial control of two requirements, use of sectoral check without require assurance, farmers with animals, CY2013 | FLAT RATE | 5,00 % | EUR | – 61 526,63 | 0,00 | – 61 526,63 | |
| Cross Compliance | 2015 | Partial control of two requirements, use of sectoral check without require assurance, farmers with animals, CY2014 | FLAT RATE | 5,00 % | EUR | – 78 725,47 | 0,00 | – 78 725,47 | |
| Cross Compliance | 2013 | SMR1 and 5 not controlled outside Natura2000 area, weakness in checks for SMR7 and SMR16, limited access to veterinarian control reports, CY2012 | ONE OFF | EUR | – 280 745,26 | – 41,98 | – 280 703,28 | ||
| Cross Compliance | 2014 | SMR1 and 5 not controlled outside Natura2000 area, weakness in checks for SMR7 and SMR16, limited access to veterinarian control reports, CY2012 | ONE OFF | EUR | – 97 287,65 | 0,00 | – 97 287,65 | ||
| Cross Compliance | 2015 | SMR1 and 5 not controlled outside Natura2000 area, weakness in checks for SMR7 and SMR16, limited access to veterinarian control reports, CY2012 | FLAT RATE | 2,00 % | EUR | – 13 600,21 | 0,00 | – 13 600,21 | |
| Cross Compliance | 2014 | SMR1 and 5 not controlled outside Natura2000 area, weakness in checks for SMR7 and SMR16, limited access to veterinarian control reports, CY2013 | ONE OFF | EUR | – 203 367,8 | 0,00 | – 203 367,8 | ||
| Cross Compliance | 2015 | SMR1 and 5 not controlled outside Natura2000 area, weakness in checks for SMR7 and SMR16, limited access to veterinarian control reports, CY2013 | FLAT RATE | 2,00 % | EUR | – 27 839,23 | 0,00 | – 27 839,23 | |
| Rural Development EAFRD (2014-2020) measures subject to IACS | 2015 | Two agri-environmental sub-measures(214): Inappropriate follow-up of the results of cross-checks in all appropriate cases with data from the IACS. | FLAT RATE | 3,00 % | EUR | – 148 200,0 | 0,00 | – 148 200,0 | |
| Total IT: | EUR | – 1 337 990,25 | – 41,98 | – 1 337 948,27 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| LT | Rural Development EAFRD Axis 4 LEADER (2007-2013) | 2013 | Deficiencies in key controls: 1) Quality of on-the-spot checks; 2) Evaluation of reasonableness of costs at application stage; 3) Eligibility of costs of the operation (in-kind contributions) | FLAT RATE | 5,00 % | EUR | – 1 288 795,9 | 0,00 | – 1 288 795,9 |
| Rural Development EAFRD Axis 4 LEADER (2007-2013) | 2014 | Deficiencies in key controls: 1) Quality of on-the-spot checks; 2) Evaluation of reasonableness of costs at application stage; 3) Eligibility of costs of the operation (in-kind contributions) | FLAT RATE | 5,00 % | EUR | – 1 530 512,9 | 0,00 | – 1 530 512,9 | |
| Rural Development EAFRD Axis 4 LEADER (2007-2013) | 2015 | Deficiencies in key controls: 1) Quality of on-the-spot checks; 2) Evaluation of reasonableness of costs at application stage; 3) Eligibility of costs of the operation (in-kind contributions) | FLAT RATE | 5,00 % | EUR | – 926 149,21 | 0,00 | – 926 149,21 | |
| Rural Development EAFRD LEADER | 2016 | Deficiencies in key controls: 1) Quality of on-the-spot checks 2) Evaluation of reasonableness of costs at application stage 3) Eligibility of costs of the operation (in-kind contributions). Correction period: 16.10.2015-31.12.2015. | FLAT RATE | 5,00 % | EUR | – 462 436,92 | 0,00 | – 462 436,92 | |
| Total LT: | EUR | – 4 207 894,93 | 0,00 | – 4 207 894,93 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| LU | Clearance of accounts — Conformity Clearance | 2010 | Non respect of the eligibility criteria | ONE OFF | 0,00 % | EUR | – 1 469 939,0 | 0,00 | – 1 469 939,0 |
| Total LU: | EUR | – 1 469 939,0 | 0,00 | – 1 469 939,0 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| MT | Certification | 2015 | Clearance of accounts FY2015 | ONE OFF | EUR | – 131 903,31 | 0,00 | – 131 903,31 | |
| Total MT: | EUR | – 131 903,31 | 0,00 | – 131 903,31 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| NL | Rural Development EAFRD Axis 4 LEADER (2007-2013) | 2014 | deficiencies in key and ancillary controls | FLAT RATE | 5,00 % | EUR | – 217 083,5 | 0,00 | – 217 083,5 |
| Rural Development EAFRD Axis 4 LEADER (2007-2013) | 2014 | deficiencies in key and ancillary controls | FLAT RATE | 7,00 % | EUR | – 89 804,68 | 0,00 | – 89 804,68 | |
| Rural Development EAFRD Axis 4 LEADER (2007-2013) | 2015 | deficiencies in key and ancillary controls | FLAT RATE | 7,00 % | EUR | – 314 873,64 | 0,00 | – 314 873,64 | |
| Rural Development EAFRD LEADER | 2016 | deficiencies in key and ancillary controls | FLAT RATE | 7,00 % | EUR | – 216 895,65 | 0,00 | – 216 895,65 | |
| Total NL: | EUR | – 838 657,47 | 0,00 | – 838 657,47 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| RO | Rural Development EAFRD Investment — private beneficiaries | 2015 | Controls on artificial conditions | FLAT RATE | 5,00 % | EUR | – 949 386,13 | 0,00 | – 949 386,13 |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Eligibility of the beneficiary — skills verification and Controls on artificial conditions | FLAT RATE | 5,00 % | EUR | – 2 661 268,1 | 0,00 | – 2 661 268,1 | |
| Rural Development EAFRD Investment — private beneficiaries | 2014 | Eligibility of the beneficiary — skills verification and Controls on artificial conditions | FLAT RATE | 5,00 % | EUR | – 648 249,31 | 0,00 | – 648 249,31 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2012 | Eligibility of the costs — respect of ceilings/aid intensity | ONE OFF | EUR | – 1 478 707,1 | – 73 935,36 | – 1 404 771,74 | ||
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Eligibility of the costs — respect of ceilings/aid intensity | ONE OFF | EUR | – 1 335 193,08 | 0,00 | – 1 335 193,08 | ||
| Rural Development EAFRD Investment — private beneficiaries | 2014 | Eligibility of the costs — respect of ceilings/aid intensity | ONE OFF | EUR | – 1 041 006,91 | 0,00 | – 1 041 006,91 | ||
| Rural Development EAFRD Axis 2 (2007-2013, area related measures) | 2010 | Execution of overlapping amount | ONE OFF | EUR | 0,00 | 5 907,74 | – 5 907,74 | ||
| Rural Development EAFRD Axis 2 (2007-2013, area related measures) | 2011 | Execution of overlapping amount | FLAT RATE | 2,00 % | EUR | 0,00 | 2 731 143,6 | – 2 731 143,6 | |
| Rural Development EAFRD Axis 2 (2007-2013, area related measures) | 2011 | Execution of overlapping amount | ONE OFF | EUR | 0,00 | 53 937,77 | – 53 937,77 | ||
| Rural Development EAFRD Axis 2 (2007-2013, area related measures) | 2012 | Execution of overlapping amount | ONE OFF | EUR | 0,00 | 15 400,0 | – 15 400,0 | ||
| Certification | 2012 | MLE for the EAFRD IACS population | ONE OFF | EUR | – 4 212 281,45 | – 83 053,09 | – 4 129 228,36 | ||
| Certification | 2012 | MLE for the EAFRD Non IACS population | ONE OFF | EUR | – 8 565 856,43 | – 852 487,19 | – 7 713 369,24 | ||
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Procurement- reasonableness of the costs check weaknesses | FLAT RATE | 2,00 % | EUR | – 508 630,52 | 0,00 | – 508 630,52 | |
| Rural Development EAFRD Axis 1+3 — Investment orientated measures (2007-2013) | 2013 | Procurement- reasonableness of the costs check weaknesses | FLAT RATE | 10,00 % | EUR | – 1 533 681,75 | 0,00 | – 1 533 681,75 | |
| Rural Development EAFRD Investment — private beneficiaries | 2014 | Procurement- reasonableness of the costs check weaknesses | FLAT RATE | 2,00 % | EUR | – 220 258,09 | 0,00 | – 220 258,09 | |
| Rural Development EAFRD Investment — private beneficiaries | 2014 | Procurement- reasonableness of the costs check weaknesses | FLAT RATE | 10,00 % | EUR | – 511 227,25 | 0,00 | – 511 227,25 | |
| Total RO: | EUR | – 23 665 746,12 | 1 796 913,47 | – 25 462 659,59 | |||||
| Member State | Measure | FY | Reason | Type | Correction % | Currency | Amount | Deductions | Financial Impact |
| SK | Certification | 2015 | Known error in the EAFRD Non-IACS population | ONE OFF | EUR | – 204 053,34 | 0,00 | – 204 053,34 | |
| Total SK: | EUR | – 204 053,34 | 0,00 | – 204 053,34 |
| Currency | Amount | Deductions | Financial Impact |
|---|---|---|---|
| EUR | – 98 799 942,4 | – 7 632 357,66 | – 91 167 584,74 |