Division BAT 2: BAT is to monitor channelled emissions to air other than from process furnaces/heaters in accordance with EN standards and with at least the minimum frequency given in the table below. If EN standards are not available, BAT is to use ISO, national or other international standards that ensure the provision of data of an equivalent scientific quality.

United Kingdom

Original text. Later amendments are not shown.

The monitoring applies where the pollutant is present in the waste gas based on the inventory of waste gas streams specified by the CWW BAT conclusions.

The minimum monitoring frequency for periodic measurements may be reduced to once every year, if the emission levels are proven to be sufficiently stable.

All (other) processes/sources where the pollutant is present in the waste gas based on the inventory of waste gas streams specified by the CWW BAT conclusions.

EN 15058 and the sampling period need adaptation so that the measured values are representative of the whole decoking cycle.

EN 13284-1 and the sampling period need adaptation so that the measured values are representative of the whole decoking cycle.

The monitoring applies where the chlorine and/or chlorinated compounds are present in the waste gas and thermal treatment is applied

Substance/ParameterProcesses/SourcesStandard(s)Minimum monitoring frequencyMonitoring associated with
BenzeneWaste gas from the cumene oxidation unit in phenol productionf1 No EN standard availableOnce every monthf2 BAT 57
All other processes/sourcesf3 BAT 10
Cl2 TDI/MDI No EN standard availableOnce every month BAT 66
EDC/VCMBAT 76
COThermal oxidiserEN 15058Once every month BAT 13
Lower olefins (decoking)No EN standard availablef4 Once every year or once during decoking, if decoking is less frequentBAT 20
EDC/VCM (decoking)BAT 78
DustLower olefins (decoking)No EN standard availablef5 Once every year or once during decoking, if decoking is less frequentBAT 20
EDC/VCM (decoking)BAT 78
All other processes/sources EN 13284-1Once every month BAT 11
EDCEDC/VCMNo EN standard availableOnce every month BAT 76
Ethylene oxideEthylene oxide and ethylene glycolsNo EN standard availableOnce every month BAT 52
FormaldehydeFormaldehydeNo EN standard availableOnce every month BAT 45
Gaseous chlorides, expressed as HClTDI/MDI EN 1911Once every month BAT 66
EDC/VCMBAT 76
All other processes/sources BAT 12
NH3 Use of SCR or SNCRNo EN standard availableOnce every month BAT 7
NOX Thermal oxidiserEN 14792Once every month BAT 13
PCDD/FTDI/MDIf6 EN 1948-1, -2, and -3Once every 6 months BAT 67
PCDD/FEDC/VCMBAT 77
SO2 All processes/sources EN 14791Once every month BAT 12
TetrachloromethaneTDI/MDI No EN standard availableOnce every month BAT 66
TVOCTDI/MDIEN 12619Once every month BAT 66
EO (desorption of CO2 from scrubbing medium)Once every 6 months BAT 51
FormaldehydeOnce every month BAT 45
Waste gas from the cumene oxidation unit in phenol productionEN 12619Once every month BAT 57
Waste gas from other sources in phenol production when not combined with other waste gas streamsOnce every year
Waste gas from the oxidation unit in hydrogen peroxide productionOnce every month BAT 86
EDC/VCMOnce every month BAT 76
All other processes/sources Once every month BAT 10
VCMEDC/VCMNo EN standard availableOnce every month BAT 76

Annotations

Footnotes

f1

The monitoring applies where the pollutant is present in the waste gas based on the inventory of waste gas streams specified by the CWW BAT conclusions.

f2

The minimum monitoring frequency for periodic measurements may be reduced to once every year, if the emission levels are proven to be sufficiently stable.

f3

All (other) processes/sources where the pollutant is present in the waste gas based on the inventory of waste gas streams specified by the CWW BAT conclusions.

f4

EN 15058 and the sampling period need adaptation so that the measured values are representative of the whole decoking cycle.

f5

EN 13284-1 and the sampling period need adaptation so that the measured values are representative of the whole decoking cycle.

f6

The monitoring applies where the chlorine and/or chlorinated compounds are present in the waste gas and thermal treatment is applied