OpenLegislation

Commission Implementing Decision (EU) 2018/304 of 27 February 2018 excluding from European Union financing certain expenditure incurred by the Member States under the European Agricultural Guarantee Fund (EAGF) and under the European Agricultural Fund for Rural Development (EAFRD) (notified under document C(2018) 955) (Only the Danish, Dutch, English, Estonian, French, Greek, Hungarian, Italian, Polish, Portuguese and Spanish texts are authentic)

EU Decision 2018/304 · Adopted 27 February 2018 · Extends to United Kingdom

Original text. legislation.gov.uk does not revise this item, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Commission Implementing Decision (EU) 2018/304

of 27 February 2018

excluding from European Union financing certain expenditure incurred by the Member States under the European Agricultural Guarantee Fund (EAGF) and under the European Agricultural Fund for Rural Development (EAFRD)

(notified under document C(2018) 955)

(Only the Danish, Dutch, English, Estonian, French, Greek, Hungarian, Italian, Polish, Portuguese and Spanish texts are authentic)

THE EUROPEAN COMMISSION,

Having regard to the Treaty on the Functioning of the European Union,

Having regard to Regulation (EU) No 1306/2013 of the European Parliament and of the Council of 17 December 2013 on the financing, management and monitoring of the common agricultural policy and repealing Council Regulations (EEC) No 352/78, (EC) No 165/94, (EC) No 2799/98, (EC) No 814/2000, (EC) No 1290/2005 and (EC) No 485/2008f1, and in particular Article 52 thereof,

After consulting the Committee on the Agricultural Funds,

Whereas:

(1)

In accordance with Article 31 of Council Regulation (EC) No 1290/2005f2 and as from 1 January 2015 in accordance with Article 52 of Regulation (EU) No 1306/2013 the Commission is to carry out the necessary verifications, communicate to the Member States the results of those verifications, take note of the comments of the Member States, initiate a bilateral discussion so that an agreement may be reached with the Member States in question, and formally communicate its conclusions to them.

(2)

The Member States have had an opportunity to request the launch of a conciliation procedure. That opportunity has been used in some cases and the reports issued on the outcome have been examined by the Commission.

(3)

In accordance with Regulation (EU) No 1306/2013, only agricultural expenditure which has been incurred in a way that has not infringed Union law may be financed.

(4)

In the light of the verifications carried out, the outcome of the bilateral discussions and the conciliation procedures, part of the expenditure declared by the Member States does not fulfil this requirement and cannot, therefore, be financed under the EAGF and the EAFRD.

(5)

The amounts that are not recognised as being chargeable to the EAGF and the EAFRD should be indicated. Those amounts do not relate to expenditure incurred more than 24 months before the Commission's written notification of the results of the verifications to the Member States.

(6)

The amounts excluded from Union financing by the present Decision should also take into account any reductions or suspensions in accordance with Article 41 of Regulation (EU) No 1306/2013 due to the fact that such reductions or suspensions are of a provisional nature and without prejudice to decisions taken pursuant to Articles 51 or 52 of that Regulation.

(7)

As regards the cases covered by this decision, the assessment of the amounts to be excluded on grounds of non-compliance with Union law was notified by the Commission to the Member States in a summary report on the subjectf3.

(8)

This Decision is without prejudice to any financial conclusions that the Commission may draw from the judgments of the Court of Justice of the European Union in cases pending on 1 December 2017,

HAS ADOPTED THIS DECISION:

Annotations to the whole text

Footnotes

f1

OJ L 347, 20.12.2013, p. 549.

f2

Council Regulation (EC) No 1290/2005 of 21 June 2005 on the financing of the common agricultural policy (OJ L 209, 11.8.2005, p. 1).

f3

Ares(2018)693441

Contents

  1. 1Article 1
  2. 2Article 2
  3. Signature
  4. Annex: Decision: 56
  5. Budget Item: 6701
  6. Budget Item: 6711

1

The amounts set out in the Annex and related to expenditure incurred by the Member States' accredited paying agencies and declared under the EAGF or the EAFRD shall be excluded from Union financing.

2

This Decision is addressed to the Kingdom of Belgium, the Kingdom of Denmark, the Republic of Estonia, the Hellenic Republic, the Kingdom of Spain, the French Republic, the Italian Republic, the Republic of Cyprus, Hungary, the Kingdom of the Netherlands, the Republic of Poland, the Portuguese Republic and the United Kingdom of Great Britain and Northern Ireland.

Signature

Done at Brussels, 27 February 2018.

For the Commission

Phil Hogan

Member of the Commission

Budget Item: 6701

Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
BE Fruit and Vegetables - Operational programmes incl withdrawals2014Deficiencies in 2 key controls: 1)‘Checks to establish the access to the aid claimed’ and 2)‘Performance of on-the-spot-checks to the sufficient number’FLAT RATE5,00 %EUR– 1 401 667,450,00– 1 401 667,45
Fruit and Vegetables - Operational programmes incl withdrawals2015Deficiencies in 2 key controls: 1)‘Checks to establish the access to the aid claimed’ and 2)‘Performance of on-the-spot-checks to the sufficient number’FLAT RATE5,00 %EUR– 3 048 613,140,00– 3 048 613,14
Fruit and Vegetables - Operational programmes incl withdrawals2016Deficiencies in 2 key controls: 1)‘Checks to establish the access to the aid claimed’ and 2)‘Performance of on-the-spot-checks to the sufficient number’FLAT RATE5,00 %EUR– 454 962,80,00– 454 962,8
Total BE: EUR – 4 905 243,39 0,00 – 4 905 243,39
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
CY Other Direct Aid - Article 68-72 of Reg.73/20092015Deficiencies in key controls on administrative checks to establish eligibility of aid, in the number and quality of OTSC and in checks of the correctness of the aid calculation, including application of penalitiesFLAT RATE25,00 %EUR– 743 559,01– 5 021,96– 738 537,05
Cross-compliance2015Execution of overlapping amountFLAT RATE10,00 %EUR0,00743,15– 743,15
Total CY: EUR – 743 559,01 – 4 278,81 – 739 280,2
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
DK Fruit and Vegetables - Operational programmes incl withdrawals2014Absence in key control: check to establish the access to the aid claimed (amendments) - Operational Programme 2013FLAT RATE10,00 %EUR– 77 482,990,00– 77 482,99
Fruit and Vegetables - Operational programmes incl withdrawals2015Absence in key control: check to establish the access to the aid claimed (amendments) - Operational Programme 2013FLAT RATE10,00 %EUR– 1 004,190,00– 1 004,19
Fruit and Vegetables - Operational programmes incl withdrawals2015Absence in key control: check to establish the access to the aid claimed (amendments) - Operational Programme 2014FLAT RATE10,00 %EUR– 50 929,210,00– 50 929,21
Fruit and Vegetables - Operational programmes incl withdrawals2016Absence in key control: check to establish the access to the aid claimed (amendments) - Operational Programme 2015FLAT RATE10,00 %EUR– 33 919,750,00– 33 919,75
Fruit and Vegetables - Operational programmes incl withdrawals2016Absence in key control: check to establish the access to the aid claimed (amendments) Operational Programme 2016FLAT RATE10,00 %EUR– 3 746,210,00– 3 746,21
Fruit and Vegetables - Operational programmes incl withdrawals2015Deficiency in key controls: Checks to establish the access to the aid claimed (approvals) and performance of on-the-spot checks to the sufficient number-Operational Programme 2014FLAT RATE5,00 %EUR– 148 588,550,00– 148 588,55
Fruit and Vegetables - Operational programmes incl withdrawals2016Deficiency in key controls: Checks to establish the access to the aid claimed (approvals) and performance of on-the-spot checks to the sufficient number-Operational Programme 2015FLAT RATE5,00 %EUR– 203 788,650,00– 203 788,65
Fruit and Vegetables - Operational programmes incl withdrawals2016Deficiency in key controls: check to establish the access to the aid claimed (approvals) and performance of on-the-spot checks to the sufficient number- Operational Programme 2016FLAT RATE5,00 %EUR– 93 947,040,00– 93 947,04
Fruit and Vegetables - Operational programmes incl withdrawals2014Deficiency in key controls: check to establish the access to the aid claimed (approvals) and performance of the on-the-spot checks to the sufficient number- Operational Programme 2013FLAT RATE5,00 %EUR– 69 031,560,00– 69 031,56
Fruit and Vegetables - Operational programmes incl withdrawals2015Deficiency in key controls: check to establish the access to the aid claimed (approvals) and performance of the on-the-spot checks to the sufficient number- Operational Programme 2013FLAT RATE5,00 %EUR– 894,660,00– 894,66
Total DK: EUR – 683 332,81 0,00 – 683 332,81
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
EE Cross-compliance2014No check of SMR1 and SMR5 outside natura2000 area and no efficient check of GAEC standard on crop rotation, CY2013FLAT RATE2,00 %EUR– 165 629,58– 8,70– 165 620,88
Cross-compliance2015No efficient check of GAEC standard on crop rotation, CY2014FLAT RATE2,00 %EUR– 222 292,54– 48,45– 222 244,09
Cross-compliance2014Weakness in the evaluation grid for the veterinarian requirements, wrong application of repetition and tolerance applied to missing eartag, CY2013ONE OFFEUR– 5 199,820,00– 5 199,82
Cross-compliance2015Weakness in the evaluation grid for the veterinarian requirements, wrong application of repetition and tolerance applied to missing eartag, CY2014ONE OFFEUR– 23 685,660,00– 23 685,66
Cross-compliance2016Weakness in the evaluation grid for the veterinarian requirements, wrong application of repetition and tolerance applied to missing eartag, CY2015ONE OFFEUR– 11 745,830,00– 11 745,83
Total EE: EUR – 428 553,43 – 57,15 – 428 496,28
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
ES Fruit and Vegetables - Operational programmes incl withdrawals2014Deficiency in check for establishing eligibility of the aid - Autonomous Community ValenciaFLAT RATE5,00 %EUR– 899 575,150,00– 899 575,15
Fruit and Vegetables - Operational programmes incl withdrawals2015Deficiency in check for establishing eligibility of the aid - Autonomous Community ValenciaFLAT RATE5,00 %EUR– 772 727,270,00– 772 727,27
Fruit and Vegetables - Operational programmes incl withdrawals2016Deficiency in check for establishing eligibility of the aid - Autonomous Community ValenciaFLAT RATE5,00 %EUR– 1 005 671,790,00– 1 005 671,79
Certification2015Known errors on EAGF NON IACS for FY 2015ONE OFFEUR– 38 949,690,00– 38 949,69
Cross-compliance2016Missing elements for SMR 16 and 17 (pigs and calves)FLAT RATE2,00 %EUR– 300 289,120,00– 300 289,12
Cross-compliance2013

Scope and quality of OTSC: Insufficient coverage of SMR 11, Missing elements SMR 16 and 17.

Reporting of findings: Inadequate control reports for GAECs and SMR 1+5

Correct application of sanctions: Leniency for SMR 7+8

FLAT RATE5,00 %EUR– 4 571,410,00– 4 571,41
Cross-compliance2014

Scope and quality of OTSC: Insufficient coverage of SMR 11, Missing elements SMR 16 and 17.

Reporting of findings: Inadequate control reports for GAECs and SMR 1+5

Correct application of sanctions: Leniency for SMR 7+8

FLAT RATE5,00 %EUR– 817 690,48– 6 308,46– 811 382,02
Cross-compliance2015

Scope and quality of OTSC: Insufficient coverage of SMR 11, Missing elements SMR 16 and 17.

Reporting of findings: Inadequate control reports for GAECs and SMR 1+5

Correct application of sanctions: Leniency for SMR 7+8

FLAT RATE5,00 %EUR– 795 478,950,00– 795 478,95
Cross-compliance2014

Scope and quality of the OTSC

Correct applications of administrative penalties

ONE OFFEUR– 305 781,24– 9 506,08– 296 275,16
Cross-compliance2015

Scope and quality of the OTSC

Correct applications of administrative penalties

ONE OFFEUR– 326 996,520,00– 326 996,52
Fruit and Vegetables - Operational programmes incl withdrawals2014Specific costs - Environmental measures - SpainONE OFFEUR– 2 354 959,99– 37 337,46– 2 317 622,53
Fruit and Vegetables - Operational programmes incl withdrawals2015Specific costs - Environmental measures - SpainONE OFFEUR– 1 410 165,940,00– 1 410 165,94
Fruit and Vegetables - Operational programmes incl withdrawals2016Specific costs - Environmental measures - SpainONE OFFEUR– 1 226 301,840,00– 1 226 301,84
Total ES: EUR – 10 259 159,39 – 53 152,0 – 10 206 007,39
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
FR Certification2015Amounts not paid to the beneficiaryONE OFFEUR– 3 582,520,00– 3 582,52
Scrutiny of transactions2015Anomalies from a control not maintained despite the lack of valid evidence in the reply from the beneficiaryONE OFFEUR– 315 360,320,00– 315 360,32
Certification2015Ceiling not applied on an promotion program expenseONE OFFEUR– 1 205,520,00– 1 205,52
Promotion Measures2015Dépenses InéligiblesONE OFFEUR– 43,230,00– 43,23
Promotion Measures2016Dépenses InéligiblesONE OFFEUR– 2 307,640,00– 2 307,64
Certification2015Error in aid calculationONE OFFEUR– 26,040,00– 26,04
Promotion Measures2011Marché PublicFLAT RATE25,00 %EUR– 12 847,810,00– 12 847,81
Promotion Measures2012Marché PublicFLAT RATE25,00 %EUR– 28 531,030,00– 28 531,03
Promotion Measures2013Marché PublicFLAT RATE25,00 %EUR– 30 952,820,00– 30 952,82
Promotion Measures2014Marché PublicFLAT RATE25,00 %EUR– 36 623,830,00– 36 623,83
Promotion Measures2015Marché PublicFLAT RATE25,00 %EUR– 33 421,850,00– 33 421,85
Promotion Measures2016Marché PublicFLAT RATE25,00 %EUR– 33 285,150,00– 33 285,15
Scrutiny of transactions2015Reverification tests - difference in amounts calculatedONE OFFEUR– 22,150,00– 22,15
Total FR: EUR – 498 209,91 0,00 – 498 209,91
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
GR Scrutiny of transactions2011Weaknesses in ex-post controls FY2011FLAT RATE0,50 %EUR– 119 748,860,00– 119 748,86
Scrutiny of transactions2012Weaknesses in ex-post controls FY2012FLAT RATE0,50 %EUR– 204 033,170,00– 204 033,17
Scrutiny of transactions2013Weaknesses in ex-post controls FY2013FLAT RATE0,50 %EUR– 166 301,760,00– 166 301,76
Scrutiny of transactions2014Weaknesses in ex-post controls FY2014FLAT RATE0,50 %EUR– 98 019,80,00– 98 019,8
Total GR: EUR – 588 103,59 0,00 – 588 103,59
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
IT Cross-compliance2015DP - CY 2014 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 29 114,62– 65,77– 29 048,85
Cross-compliance2016DP - CY 2014 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 267,750,00– 267,75
Cross-compliance2016DP - CY 2015 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 39 163,320,00– 39 163,32
Cross-compliance2017DP - CY 2015 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 679,350,00– 679,35
Milk - Schoolmilk2014Incomplete on-the-spot checks: weakness in the quality of on the-spot checks (key control); absence of verification (during on-the-spot checks) of the existence, contents and location of the European school milk poster (ancillary control)FLAT RATE5,00 %EUR– 88 557,310,00– 88 557,31
Milk - Schoolmilk2015Incomplete on-the-spot checks: weakness in the quality of on the-spot checks (key control); absence of verification (during on-the-spot checks) of the existence, contents and location of the European school milk poster (ancillary control)FLAT RATE5,00 %EUR– 105 852,810,00– 105 852,81
Milk - Schoolmilk2016Incomplete on-the-spot checks: weakness in the quality of on the-spot checks (key control); absence of verification (during on-the-spot checks) of the existence, contents and location of the European school milk poster (ancillary control)FLAT RATE5,00 %EUR– 84 911,30,00– 84 911,3
Apiculture2014No supervision of the tasks delegated to regional administrations and ministries: absence of adequate supervision of the procedure (ancillary control) and absence of assessment of the results of the controls performed (ancillary control)FLAT RATE2,00 %EUR– 55 066,50,00– 55 066,5
Apiculture2015No supervision of the tasks delegated to regional administrations and ministries: absence of adequate supervision of the procedure (ancillary control) and absence of assessment of the results of the controls performed (ancillary control)FLAT RATE2,00 %EUR– 54 104,650,00– 54 104,65
Total IT: EUR – 457 717,61 – 65,77 – 457 651,84
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
PT Irregularities2014Debts wrongly reported in the Annex III tables, having escaped the application of the 50/50 ruleONE OFFEUR– 1 052 101,050,00– 1 052 101,05
Irregularities2014Delays observed in the recovery proceedings for cases taken over by IFAP from a previous Paying AgencyONE OFFEUR– 741 737,970,00– 741 737,97
Irregularities2014delays observed in the recovery proceedings regarding individual casesONE OFFEUR– 104 962,960,00– 104 962,96
Decoupled Direct Aids2015Weakness in cross checks and on-the-spot checks - claim year 2014FLAT RATE5,00 %EUR– 3 242 209,730,00– 3 242 209,73
Decoupled Direct Aids2016Weakness in cross checks and on-the-spot checks - claim year 2014FLAT RATE5,00 %EUR– 3 715,50,00– 3 715,5
Decoupled Direct Aids2016Weakness in cross checks and on-the-spot checks - claim year 2015FLAT RATE2,00 %EUR– 884 717,490,00– 884 717,49
Decoupled Direct Aids2016Weakness in cross checks and on-the-spot checks - claim year 2015FLAT RATE5,00 %EUR– 3 590 150,340,00– 3 590 150,34
Total PT: EUR – 9 619 595,04 0,00 – 9 619 595,04
CurrencyAmountDeductionsFinancial Impact
EUR – 28 183 474,18– 57 553,73– 28 125 920,45

Budget Item: 6711

Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
EE Cross-compliance2014No check of SMR1 and SMR5 outside natura2000 area and no efficient check of GAEC standard on crop rotation, CY2013FLAT RATE2,00 %EUR– 77 416,430,00– 77 416,43
Cross-compliance2015No efficient check of GAEC standard on crop rotation, CY2014FLAT RATE2,00 %EUR– 19 774,20,00– 19 774,2
Total EE: EUR – 97 190,63 0,00 – 97 190,63
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
ES Certification2015Correction related to the MLE on EAFRDONE OFFEUR– 668 699,810,00– 668 699,81
Certification2015Financial correction corresponding to known error on EAFRD non IACS for FY 2015ONE OFFEUR– 11 440,010,00– 11 440,01
Certification2015Financial correction for EAFRD NON IACS for FY 2015ONE OFFEUR– 113 175,10,00– 113 175,1
Cross-compliance2016Missing elements for SMR 16 and 17 (pigs and calves)FLAT RATE2,00 %EUR– 21 343,860,00– 21 343,86
Cross-compliance2013

Scope and quality of OTSC: Insufficient coverage of SMR 11, Missing elements SMR 16 and 17.

Reporting of findings: Inadequate control reports for GAECs and SMR 1+5

Correct application of sanctions: Leniency for SMR 7+8

FLAT RATE5,00 %EUR– 762,380,00– 762,38
Cross-compliance2014

Scope and quality of OTSC: Insufficient coverage of SMR 11, Missing elements SMR 16 and 17.

Reporting of findings: Inadequate control reports for GAECs and SMR 1+5

Correct application of sanctions: Leniency for SMR 7+8

FLAT RATE5,00 %EUR– 62 486,640,00– 62 486,64
Cross-compliance2015

Scope and quality of OTSC: Insufficient coverage of SMR 11, Missing elements SMR 16 and 17.

Reporting of findings: Inadequate control reports for GAECs and SMR 1+5

Correct application of sanctions: Leniency for SMR 7+8

FLAT RATE5,00 %EUR– 59 547,370,00– 59 547,37
Cross-compliance2016

Scope and quality of OTSC: Insufficient coverage of SMR 11, Missing elements SMR 16 and 17.

Reporting of findings: Inadequate control reports for GAECs and SMR 1+5

Correct application of sanctions: Leniency for SMR 7+8

FLAT RATE5,00 %EUR– 921,490,00– 921,49
Total ES: EUR – 938 376,66 0,00 – 938 376,66
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
FR Rural Development EAFRD Axis 4 LEADER (2007-2013)2014Weaknesses in the operation of 5 key controls and absence in the operation of one ancillary control.FLAT RATE10,00 %EUR– 2 027 152,90,00– 2 027 152,9
Rural Development EAFRD Leader2015Weaknesses in the operation of 5 key controls and absence in the operation of one ancillary control.FLAT RATE10,00 %EUR– 8 656 384,250,00– 8 656 384,25
Rural Development EAFRD Leader2016Weaknesses in the operation of 5 key controls and absence in the operation of one ancillary control.FLAT RATE10,00 %EUR– 4 018 872,630,00– 4 018 872,63
Total FR: EUR – 14 702 409,78 0,00 – 14 702 409,78
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
GB Certification2015Clearance of accounts EAFRD last year of execution Q1-Q5 - established ‘known error’ONE OFFEUR– 213 546,870,00– 213 546,87
Total GB: EUR – 213 546,87 0,00 – 213 546,87
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
GR Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2012deficiency in verification of reasonableness of costsFLAT RATE5,00 %EUR– 120 897,570,00– 120 897,57
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2013deficiency in verification of reasonableness of costsFLAT RATE5,00 %EUR– 303 292,010,00– 303 292,01
Rural Development EAFRD Investment - private beneficiaries2014deficiency in verification of reasonableness of costsFLAT RATE5,00 %EUR– 553 152,710,00– 553 152,71
Rural Development EAFRD Investment - private beneficiaries2015deficiency in verification of reasonableness of costsFLAT RATE5,00 %EUR– 437 893,870,00– 437 893,87
Rural Development EAFRD Investment - private beneficiaries2016deficiency in verification of reasonableness of costsFLAT RATE5,00 %EUR– 822 852,070,00– 822 852,07
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2010inapropriate procedures for the selection of projectsFLAT RATE5,00 %EUR– 30 749,910,00– 30 749,91
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2011inapropriate procedures for the selection of projectsFLAT RATE5,00 %EUR– 49 826,520,00– 49 826,52
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2012inapropriate procedures for the selection of projectsFLAT RATE5,00 %EUR– 119 551,880,00– 119 551,88
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2013inapropriate procedures for the selection of projectsFLAT RATE5,00 %EUR– 201 254,10,00– 201 254,1
Rural Development EAFRD Investment - public beneficiaries2014inapropriate procedures for the selection of projectsFLAT RATE5,00 %EUR– 830 312,290,00– 830 312,29
Rural Development EAFRD Investment - public beneficiaries2014inapropriate procedures for the selection of projectsFLAT RATE10,00 %EUR– 6 136 480,210,00– 6 136 480,21
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2015inapropriate procedures for the selection of projectsFLAT RATE5,00 %EUR– 703 301,490,00– 703 301,49
Rural Development EAFRD (2014-2020) Investment - private beneficiaries2015inapropriate procedures for the selection of projectsFLAT RATE10,00 %EUR– 2 155 409,320,00– 2 155 409,32
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2010Inapropriate procedures for the selection of projectsFLAT RATE10,00 %EUR– 554 055,15– 487 979,28– 66 075,87
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2011Inapropriate procedures for the selection of projectsFLAT RATE10,00 %EUR– 1 220 515,76– 656 150,49– 564 365,27
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2012Inapropriate procedures for the selection of projectsFLAT RATE10,00 %EUR– 1 828 268,31– 996 721,66– 831 546,65
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2013Inapropriate procedures for the selection of projectsFLAT RATE10,00 %EUR– 1 801 318,58– 871 203,34– 930 115,24
Total GR: EUR – 17 869 131,75 – 3 012 054,77 – 14 857 076,98
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
HU Rural Development EAFRD Technical Assistance (2007-2013)2014Administrative checks on eligibility of expenditure and reasonableness of costs – expenditure for the National Rural Network secretariatFLAT RATE5,00 %EUR– 9 628,570,00– 9 628,57
Rural Development EAFRD Technical Assistance (2007-2013)2015Administrative checks on eligibility of expenditure and reasonableness of costs – expenditure for the National Rural Network secretariatFLAT RATE5,00 %EUR– 58 417,950,00– 58 417,95
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2016Administrative checks on eligibility of expenditure and reasonableness of costs – expenditure for the National Rural Network secretariatFLAT RATE5,00 %EUR– 21 014,370,00– 21 014,37
Rural Development EAFRD Investment - public beneficiaries2014Deficiencies in key control ‘verification that public procurement procedures are in compliance with relevant procurement rules’FLAT RATE3,00 %EUR– 1 689 987,980,00– 1 689 987,98
Rural Development EAFRD (2014-2020) Investment - private beneficiaries2015Deficiencies in key control ‘verification that public procurement procedures are in compliance with relevant procurement rules’FLAT RATE3,00 %EUR– 159 748,420,00– 159 748,42
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2015Deficiencies in key control ‘verification that public procurement procedures are in compliance with relevant procurement rules’FLAT RATE3,00 %EUR– 1 369 614,850,00– 1 369 614,85
Rural Development EAFRD (2014-2020) Measures with flat-rate support2015Deficiencies in key control ‘verification that public procurement procedures are in compliance with relevant procurement rules’FLAT RATE3,00 %EUR– 934 232,550,00– 934 232,55
Rural Development EAFRD (2014-2020) Investment - private beneficiaries2016Deficiencies in key control ‘verification that public procurement procedures are in compliance with relevant procurement rules’FLAT RATE3,00 %EUR– 25 148,560,00– 25 148,56
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2016Deficiencies in key control ‘verification that public procurement procedures are in compliance with relevant procurement rules’FLAT RATE3,00 %EUR– 335 499,230,00– 335 499,23
Rural Development EAFRD (2014-2020) Measures with flat-rate support2016Deficiencies in key control ‘verification that public procurement procedures are in compliance with relevant procurement rules’FLAT RATE3,00 %EUR– 108 319,820,00– 108 319,82
Rural Development EAFRD (2014-2020) Investment - private beneficiaries2016Deficiency in the verification of the selection criteriaFLAT RATE5,00 %EUR– 1 049 828,990,00– 1 049 828,99
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2013Deficiency in the verification of the selection criterionsFLAT RATE5,00 %EUR– 2 107 770,830,00– 2 107 770,83
Rural Development EAFRD Investment - private beneficiaries2014Deficiency in the verification of the selection criterionsFLAT RATE5,00 %EUR– 3 591 328,190,00– 3 591 328,19
Rural Development EAFRD Investment - private beneficiaries2015Deficiency in the verification of the selection criterionsFLAT RATE5,00 %EUR– 3 760 449,180,00– 3 760 449,18
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2015Ineligible expenditure - ‘rehabilitation allowance’ONE OFFEUR– 78 404,090,00– 78 404,09
Total HU: EUR – 15 299 393,58 0,00 – 15 299 393,58
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
IT Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2012M121 - Evaluation of the reasonableness of costs using a suitable evaluation systemFLAT RATE5,00 %EUR– 1 050,850,00– 1 050,85
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2013M121 & M311 - Evaluation of the reasonableness of costs using a suitable evaluation systemFLAT RATE5,00 %EUR– 44 795,620,00– 44 795,62
Rural Development EAFRD Investment - private beneficiaries2014M121 & M311 - Evaluation of the reasonableness of costs using a suitable evaluation systemFLAT RATE5,00 %EUR– 683 051,220,00– 683 051,22
Rural Development EAFRD Axis 1+3 - Investment orientated measures (2007-2013)2013M123 - Evaluation of the reasonableness of costs using a suitable evaluation systemFLAT RATE5,00 %EUR– 69 906,410,00– 69 906,41
Rural Development EAFRD Investment - private beneficiaries2014M123 - Evaluation of the reasonableness of costs using a suitable evaluation systemFLAT RATE5,00 %EUR– 187 357,160,00– 187 357,16
Rural Development EAFRD (2014-2020) measures subject to IACS2016Measure 10 - Insufficient information in the on-the-spot check reports.FLAT RATE2,00 %EUR– 372 560,230,00– 372 560,23
Cross-compliance2015RD - CY 2014 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 424,780,00– 424,78
Cross-compliance2016RD - CY 2014 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 11 664,440,00– 11 664,44
Cross-compliance2017RD - CY 2014 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 6,640,00– 6,64
Cross-compliance2016RD - CY 2015 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 22 843,510,00– 22 843,51
Cross-compliance2017RD - CY 2015 - Absent checks of SMR 12 - Deficient checks of SMR 11FLAT RATE2,00 %EUR– 2 984,280,00– 2 984,28
Total IT: EUR – 1 396 645,14 0,00 – 1 396 645,14
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
NL Rural Development EAFRD Axis 2 (2007-2013, non area related measures)2014Measure 216 - FY 2014: Verification that public procurement procedures are in compliance with national and Union RegulationONE OFFEUR– 73 468,750,00– 73 468,75
Rural Development EAFRD (2014-2020) Investment - private beneficiaries2015Measure 216 - FY 2015: Verification that public procurement procedures are in compliance with national and Union RegulationONE OFFEUR– 41 982,050,00– 41 982,05
Total NL: EUR – 115 450,8 0,00 – 115 450,8
Member StateMeasureFYReasonTypeCorrection %CurrencyAmountDeductionsFinancial Impact
PL Rural Development EAFRD Technical Assistance (2007-2013)2013deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to procurement costsFLAT RATE5,00 %EUR– 611 934,310,00– 611 934,31
Rural Development EAFRD Technical Assistance (2007-2013)2014deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to procurement costsFLAT RATE5,00 %EUR– 225 106,610,00– 225 106,61
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2015deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to procurement costsFLAT RATE5,00 %EUR– 452 711,750,00– 452 711,75
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2016deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to procurement costsFLAT RATE5,00 %EUR– 24 793,370,00– 24 793,37
Rural Development EAFRD Technical Assistance (2007-2013)2013deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to staff costsFLAT RATE5,00 %EUR– 364 619,660,00– 364 619,66
Rural Development EAFRD Technical Assistance (2007-2013)2014deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to staff costsFLAT RATE5,00 %EUR– 1 268 615,210,00– 1 268 615,21
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2015deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to staff costsFLAT RATE5,00 %EUR– 998 547,680,00– 998 547,68
Rural Development EAFRD (2014-2020) Investment - public beneficiaries2016deficiencies found as regards administrative checks implemented by Poland for Technical assistance under the RDP 2007-2013 related to staff costsFLAT RATE5,00 %EUR– 806 758,570,00– 806 758,57
Total PL: EUR – 4 753 087,16 0,00 – 4 753 087,16
CurrencyAmountDeductionsFinancial Impact
EUR – 55 385 232,37– 3 012 054,77– 52 373 177,6