Article 6 Project execution stage: duties of coordinators
United Kingdom
The coordinator(s) for safety and health matters during the project execution stage appointed in accordance with Article 3 (1) shall:
- (a)
coordinate implementation of the general principles of prevention and safety:
-
when technical and/or organizational aspects are being decided, in order to plan the various items or stages of work which are to take place simultaneously or in succession,
-
when estimating the period required for completing such work or work stages;
-
- (b)
coordinate implementation of the relevant provisions in order to ensure that employers and, if necessary for the protection of workers, self-employed persons:
-
apply the principles referred to in Article 8 in a consistent manner,
-
where required, follow the safety and health plan referred to in Article 5 (b);
-
- (c)
make, or cause to be made, any adjustments required to the safety and health plan referred to in Article 5 (b) and the file referred to in Article 5 (c) to take account of the progress of the work and any changes which have occurred;
- (d)
organize cooperation between employers, including successive employers on the same site, coordination of their activities with a view to protecting workers and preventing accidents and occupational health hazards and reciprocal information as provided for in Article 6 (4) of Directive 89/391/EEC, ensuring that self-employed persons are brought into this process where necessary;
- (e)
coordinate arrangements to check that the working procedures are being implemented correctly;
- (f)
take the steps necessary to ensure that only X1authorized persons are allowed onto the construction site.