Council Directive 92/57/EEC of 24 June 1992 on the implementation of minimum safety and health requirements at temporary or mobile constructions sites (eighth individual Directive within the meaning of Article 16 (1) of Directive 89/391/EEC)
EU Directive 1992/57 · Adopted 24 June 1992 · Extends to United Kingdom
Council Directive 92/57/EEC
of 24 June 1992
on the implementation of minimum safety and health requirements at temporary or mobile constructions sites (eighth individual Directive within the meaning of Article 16 (1) of Directive 89/391/EEC)
THE COUNCIL OF THE EUROPEAN COMMUNITIES,
Having regard to the Treaty establishing the European Economic Community, and in particular Article 118a thereof,
Having regard to the proposal from the Commissionf1, submitted after consulting the Advisory Committee on Safety, Hygiene and Health Protection at Work,
In cooperation with the European Parliamentf2,
Having regard to the opinion of the Economic and Social Committeef3,
Whereas Article 118 a of the Treaty provides that the Council shall adopt, by means of directives, minimum requirements for encouraging improvements, especially in the working environment, to ensure a better level of protection of the safety and health of workers;
Whereas, under the terms of that Article, those directives are to avoid imposing administrative, financial and legal constraints in a way which would hold back the creation and development of small and medium-sized undertakings;
Whereas the communication from the Commission on its programme concerning safety, hygiene and health at workf4 provides for the adoption of a Directive designed to guarantee the safety and health of workers at temporary or mobile construction sites;
Whereas, in its resolution of 21 December 1987 on safety, hygiene and health at workf5, the Council took note of the Commission's intention of submitting to the Council in the near future minimum requirements concerning temporary or mobile construction sites;
Whereas temporary or mobile construction sites constitute an area of activity that exposes workers to particularly high levels of risk;
Whereas unsatisfactory architectural and/or organizational options or poor planning of the works at the project preparation stage have played a role in more than half of the occupational accidents occurring on construction sites in the Community;
Whereas in each Member State the authorities responsible for safety and health at work must be informed, before the beginning of the works, of the execution of works the scale of which exceeds a certain threshold;
Whereas, when a project is being carried out, a large number of occupational accidents may be caused by inadequate coordination, particularly where various undertakings work simultaneously or in succession at the same temporary or mobile construction site;
Whereas it is therefore necessary to improve coordination between the various parties concerned at the project preparation stage and also when the work is being carried out;
Whereas compliance with the minimum requirements designed to guarantee a better standard of safety and health at temporary or mobile construction sites is essential to ensure the safety and health of workers;
Whereas, moreover, self-employed persons and employers, where they are personally engaged in work activity, may, through their activities on a temporary or mobile construction site, jeopardize the safety and health of workers;
Whereas it is therefore necessary to extend to self-employed persons and to employers where they are personally engaged in work activity on the site certain relevant provisions of Council Directive 89/655/EEC of 30 November 1989 concerning the minimum safety and health requirements for the use of work equipment by workers at work (second individual Directive)f6, and of Council Directive 89/656/EEC of 30 November 1989 on the minimum health and safety requirements for the use by workers of personal protective equipment at the workplace (third individual Directive)f7;
Whereas this Directive is an individual Directive within the meaning of Article 16 (1) of Council Directive 89/391/EEC of 12 June 1989 on the introduction of measures to encourage improvements in the safety and health of workers at workf8; whereas, therefore, the provisions of the said Directive are fully applicable to temporary or mobile construction sites, without prejudice to more stringent and/or specific provisions contained in this Directive;
Whereas this Directive constitutes a practical step towards the achievement of the social dimension of the internal market with special reference to the subject matter of Council Directive 89/106/EEC of 21 December 1988 on the approximation of laws, regulations and administrative provisions of the Member States relating to construction productsf9 and the subject matter covered by Council Directive 89/440/EEC of 18 July 1989 amending Direaive 71/305/EEC concerning coordination of procedures for the award of public work contractsf10;
Whereas, pursuant to Council Decision 74/325/EECf11, the Advisory Committee on Safety, Hygiene and Health Protection at Work is consulted by the Commission with a view to drawing up proposals in this field,
HAS ADOPTED THIS DIRECTIVE:
Annotations to the whole text
Footnotes
- f1
-
OJ No C 213, 28.8.1990, p. 2 and OJ No C 112, 27.4.1991, p. 4.
- f2
- f3
- f4
- f5
- f6
- f7
- f8
- f9
- f10
-
OJ No L 210, 21.7.1989, p. 1. Amended by Commission Decision 90/380/EEC (OJ No L 187, 19.7.1990, p. 55).
- f11
-
OJ No L 185, 9.7.1974, p. 15. Last amended by the 1985 Act of Accession.
Contents
- 1Subject
- 2Definitions
- 3Appointment of coordinators — Safety and health plan — Prior notice
- 4Project preparation stage: general principles
- 5Project preparation stage: duties of coordinators
- 6Project execution stage: duties of coordinators
- 7Responsibilities of clients, project supervisors and employers
- 8Implementation of Article 6 of Directive 89/391/EEC
- 9Obligations of employers
- 10Obligations of other groups of persons
- 11Information for workers
- 12Consultation and participation of workers
- 13Amendments to Annex IV
- 13aExercise of the delegation
- 13bUrgency procedure
- 14Final Provisions
- 15Article 15
- Annex I: NON-EXHAUSTIVE LIST OF BUILDING AND CIVIL ENGINEERING WORKS REFERRED TO IN ARTICLE 2 (a) OF THE DIRECTIVE
- 1Division 1
- 2Division 2
- 3Division 3
- 4Division 4
- 5Division 5
- 6Division 6
- 7Division 7
- 8Division 8
- 9Division 9
- 10Division 10
- 11Division 11
- 12Division 12
- 13Division 13
- Annex II: NON-EXHAUSTIVE LIST OF WORK INVOLVING PARTICULAR RISKS TO THE SAFETY AND HEALTH OF WORKERS REFERRED TO IN ARTICLE 3 (2), SECOND PARAGRAPH OF THE DIRECTIVE
- 1Division 1
- 2Division 2
- 3Division 3
- 4Division 4
- 5Division 5
- 6Division 6
- 7Division 7
- 8Division 8
- 9Division 9
- 10Division 10
- Annex IIICONTENT OF THE PRIOR NOTICE REFERRED TO IN ARTICLE 3 (3), FIRST PARAGRAPH OF THE DIRECTIVE
- Annex IV: MINIMUM SAFETY AND HEALTH REQUIREMENTS FOR CONSTRUCTION SITES
- Preliminary remarks
- GENERAL MINIMUM REQUIREMENTS FOR ON-SITE WORKPLACES
- Stability and solidity
- 1.1Division 1.1
- 1.2Division 1.2
- Energy distribution installations
- 2.1Division 2.1
- 2.2Division 2.2
- Emergency routes and exits
- 3.1Division 3.1
- 3.2Division 3.2
- 3.3Division 3.3
- 3.4Division 3.4
- 3.5Division 3.5
- 3.6Division 3.6
- Fire detection and fire fighting
- 4.1Division 4.1
- 4.2Division 4.2
- 4.3Division 4.3
- 5Ventilation
- Exposure to particular risks
- 6.1Division 6.1
- 6.2Division 6.2
- 6.3Division 6.3
- 7Temperature
- Natural and artificial lighting of workstations, rooms and traffic routes on the site
- 8.1Division 8.1
- 8.2Division 8.2
- 8.3Division 8.3
- Doors and gates
- 9.1Division 9.1
- 9.2Division 9.2
- 9.3Division 9.3
- 9.4Division 9.4
- 9.5Division 9.5
- Traffic routes — danger areas
- 10.1Division 10.1
- 10.2Division 10.2
- 10.3Division 10.3
- 10.4Division 10.4
- Loading bays and ramps
- 11.1Division 11.1
- 11.2Division 11.2
- 11.3Division 11.3
- 12Freedom of movement at the workstation
- First aid
- 13.1Division 13.1
- 13.2Division 13.2
- 13.3Division 13.3
- 13.4Division 13.4
- Sanitary equipment
- Changing rooms and lockers.
- 14.1.1Appropriate changing rooms must be provided for workers if they have to wear special work clothes and if, for reasons of health or propriety, they cannot be expected to change in another area.
- 14.1.2Changing rooms must be sufficiently large and have facilities to enable each worker, where necessary, to dry his working clothes as well as his own clothing and personal effects and to lock them away.
- 14.1.3Division 14.1.3
- 14.1.4Division 14.1.4
- Showers and washbasins
- 14.2.1Suitable showers in sufficient numbers must be provided for workers if required by the nature of the work or for health reasons.
- 14.2.2The shower rooms must be sufficiently large to permit each worker to wash without hindrance in conditions of an appropriate standard of hygiene.
- 14.2.3Where showers are not required under the first paragraph of 14.2.1, a sufficient number of suitable washbasins with running water (hot water if necessary) must be provided in the vicinity of the workstations and the changing rooms.
- 14.2.4Division 14.2.4
- 14.3Lavatories and washbasins
- Rest rooms and/or accommodation areas
- 15.1Division 15.1
- 15.2Division 15.2
- 15.3Division 15.3
- 15.4Division 15.4
- 15.5Division 15.5
- 16Pregnant women and nursing mothers
- 17Handicapped workers
- Miscellaneous provisions
- 18.1Division 18.1
- 18.2Division 18.2
- 18.3Division 18.3
- SPECIFIC MINIMUM REQUIREMENTS FOR ON-SITE WORKSTATIONS
- Preliminary remark
- On-site indoor workstations
- 1Stability and solidity
- 2Emergency doors
- 3Ventilation
- Temperature
- 4.1Division 4.1
- 4.2Division 4.2
- 5Natural and artificial lighting
- Floors, walls, ceilings and roofs of rooms
- 6.1Division 6.1
- 6.2Division 6.2
- 6.3Division 6.3
- Windows and skylights
- 7.1Division 7.1
- 7.2Division 7.2
- Doors and Gates
- 8.1Division 8.1
- 8.2Division 8.2
- 8.3Division 8.3
- 8.4Division 8.4
- 9Traffic routes
- 10Specific measures for escalators and travelators
- 11Room dimensions and air space in rooms
- On-site outdoor workstations
- Stability and solidity
- 1.1Division 1.1
- 1.2Checking
- Energy distribution installations
- 2.1Division 2.1
- 2.2Division 2.2
- 2.3Division 2.3
- 3Atmospheric influences
- 4Falling objects
- Falls from a height
- 5.1Division 5.1
- 5.2Division 5.2
- Scaffolding and leaders
- 6.1Division 6.1
- 6.2Division 6.2
- 6.3Division 6.3
- 6.4Division 6.4
- 6.5Division 6.5
- Lifting equpiment
- 7.1Division 7.1
- 7.2Division 7.2
- 7.3Division 7.3
- Excavating and materials-handling vehicles and machinery
- 8.1Division 8.1
- 8.2Division 8.2
- 8.3Division 8.3
- 8.4Division 8.4
- Installations, machinery, equipment
- 9.1Division 9.1
- 9.2Division 9.2
- Excavations, wells, underground works, tunnels and earthworks
- 10.1Division 10.1
- 10.2Division 10.2
- 10.3Division 10.3
- 10.4Division 10.4
- 11Demolition work
- Metal or concrete frameworks, shutterings and heavy prefabricated components
- 12.1Division 12.1
- 12.2Division 12.2
- 12.3Division 12.3
- Cofferdams and caissons
- 13.1Division 13.1
- 13.2Division 13.2
- 13.3Division 13.3
- Work on roofs
- 14.1Division 14.1
- 14.2Division 14.2