1.

The provisions of paragraphs 2 to 8 shall apply in the case of supply ex works or free carrier. The stage of delivery shall be laid down in the tender notice.

2.

The supplier shall reach a written agreement with the beneficiary or his representative on the date for delivery of the goods to the loading address specified in his tender or the tender notice and send a copy to the monitor. The monitor shall provide any assistance which may be necessary in order for such agreement to be reached.

The goods may not be delivered in split consignments unless the beneficiary and the Commission so agree. In that case the Commission shall require the supplier to bear the additional checking costs.

3.

The supplier shall notify the monitor and the Commission promptly in writing of the agreed date and place of delivery, or of the fact that agreement with the beneficiary has not been reached. Failure to reach agreement with the beneficiary must be notified at the latest ten days before the deadline set in the tender notice, so that the Commission can take appropriate steps.

4.

The supply must be carried out by the deadline set in the tender notice. Where delivery is impossible before that deadline, the Commission, at the written request of the beneficiary, backed up by appropriate supporting evidence, may extend the deadline by up to 30 days in order to allow delivery to take place. The supplier shall be obliged to accept the extension.

Where the supply cannot take place by the extended deadline for reasons not attributable to the supplier, he may, at his request, be released from his obligations.

5.

The supply shall be complete when all the goods have actually been loaded and stowed on the means of transport provided by the beneficiary.

6.

The supplier shall bear all risks, including loss or deterioration, to which the goods may be subject until completion of the supply and recording of that fact by the monitor in the final certificate of conformity referred to in Article 16.

7.

The supplier shall carry out the formalities relating to the export license and customs clearance, bearing the related costs and charges.

8.

In the event of a discrepancy between the dates and quantities entered in the taking-over certificate referred to in Article 17 and the final certificate of conformity, the Commission may carry out further checks on the basis of which new documents may be issued.