Article 13
United Kingdom
The provisions of paragraphs 2 to 8 shall apply in the case of supply free at port of shipment. The stage of delivery shall be specified in the tender notice.
The supplier shall reach a written agreement with the beneficiary or his representative on the date for delivery of the goods at the port of shipment specified in his tender, and on the loading wharf and, where applicable, the loading rate, and send a copy to the monitor. The monitor shall provide any assistance which may be necessary in order for such agreement to be reached. In the event of failure to reach an agreement the Commission shall take the appropriate measures on the basis of a report from the monitor.
At the supplier's written request, with the agreement of the beneficiary, the Commission may authorize the port of shipment to be changed provided any costs this entails are borne by the supplier.
The goods may not be delivered in split consignments unless the beneficiary and the Commission so agree. In that case, the Commission shall require the supplier to bear the additional checking costs.
The supplier shall notify the monitor and the Commission promptly in writing of the agreed date and place of delivery, or of the fact that agreement with the beneficiary has not been reached. Failure to reach agreement with the beneficiary must be notified at the latest 10 days before the deadline set in the tender notice, so that the Commission can take appropriate steps.
Where it has proved impossible to carry out the delivery by the deadline set in the tender notice because of the absence of a sea connection, the Commission shall take appropriate measures on the basis of a report from the monitor. Such measures may consist of automatic extension of the delivery period, permission to use another port, cancellation of the supply operation, or shipping of the goods on a vessel proposed by the supplier or the monitor, provided freight and loading charges are deemed to be acceptable. The supplier may bear the costs entailed if the confirmation referred to in Article 7 (6) proves to be incorrect.
Except in the circumstances described in paragraph 4, the delivery must be carried out by the deadline set in the tender notice. Where delivery is impossible by that deadline, the Commission, at the written request of the beneficiary, backed up by appropriate supporting evidence, may extend the deadline by up to 30 days in order to allow delivery to take place. The supplier shall be obliged to accept the extension.
Where the delivery cannot take place by the extended deadline, for reasons not attributable to the supplier, he may, at his request, be released from his obligations.
Where the loading operations are the responsibility of the supplier, he shall load the goods onto the vessel at the vessel's or the port installation's loading rate, as appropriate, in accordance with the custom of the port.
In the case of delivery FOB stowed, the supplier shall be responsible for all subsequent stowage and, in the case of bulk delivery, trimming operations.
The supply shall be complete when all the goods have actually been delivered at the stage specified in the tender notice.
Article 12 (6), (7) and (8) shall apply mutatis mutandis.