OpenLegislation

Article 46 Closure of the programme

United Kingdom

Original text. Later amendments are not shown.

1.

A joint operational programme shall be considered closed after:

(a)

all the contracts concluded under the programme have been closed;

(b)

the final balance has been paid or reimbursed;

(c)

remaining appropriations have been decommitted by the Commission.

2.

The closure of the operational programme shall not prejudice the Commission's right to undertake, at a later stage, financial corrections vis-à-vis the Joint Managing Authority or the project beneficiaries if the final amount of the programme or the projects has to be readjusted as a result of controls carried out after the closure date.

F13.

Where the Joint Managing Authority has not been able to declare to the Commission final amounts because of:

(a)

projects suspended by a legal proceeding or by an administrative appeal having suspensory effect; or

(b)

reasons of force majeure seriously affecting the implementation of all or part of the programme;

the ending date of the execution period as set in paragraph 1 of Article 43 shall not apply to part of the programme concerned by points (a) or (b) of this paragraph.

Annotations

Textual amendments

F1

Inserted by Commission Implementing Regulation (EU) 2017/2011 of 9 November 2017 amending Regulation (EC) No 951/2007 laying down implementing rules for cross-border cooperation programmes financed under Regulation (EC) No 1638/2006 of the European Parliament and of the Council.