Firm renomination is permitted up to 90 % and down to 10 % of the contracted capacity by the network user at the interconnection point. However, if the nomination exceeds 80 % of the contracted capacity, half of the non-nominated volume may be renominated upwards. If the nomination does not exceed 20 % of the contracted capacity, half of the nominated volume may be renominated downwards. The application of this paragraph is without prejudice to the applicable emergency measures.

Annotations

Textual amendments

F1

Substituted by Commission Decision of 24 August 2012 on amending Annex I to Regulation (EC) No 715/2009 of the European Parliament and of the Council on conditions for access to the natural gas transmission networks (Text with EEA relevance) (2012/490/EU).