Article 22A Transitional measures for ongoing applications submitted before IP completion dayF1
This Article applies where an application was made before IP completion day to a Member State in accordance with Article 3 and accepted under Article 4 of Regulation (EU) No 1062/2014 or Article 9 of Regulation (EC) No 1451/2007 as they had effect immediately before IP completion day and where a decision on approval has not been made before IP completion day.
The application will be treated as having been received under Article 4 of this Regulation as it has effect in F2assimilated law if the participant resubmits their application and supporting dossier to the competent authority within:
90 days after IP completion day where the United Kingdom competent authority was the evaluating competent authority prior to 30 March 2019; or
180 days after IP completion day where the United Kingdom competent authority was not the evaluating competent authority prior to 30 March 2019.
Where the applicant does not meet the requirements of this Article, the application is to be treated as having been withdrawn under Article 11(1)(b).
Annotations
Textual amendments
- F1
Arts. 22A-22D inserted (31.12.2020) by The Chemicals (Health and Safety) and Genetically Modified Organisms (Contained Use) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/720), reg. 1(2), Sch. 2 para. 235 (as amended by S.I. 2020/1567, reg. 1(2), Sch. 2 para. 72); 2020 c. 1, Sch. 5 para. 1(1)
- F2
Word in Art. 22A(2) substituted (27.2.2025) by The Retained EU Law (Revocation and Reform) Act 2023 (Consequential Amendments) Regulations 2025 (S.I. 2025/82), reg. 1(2), Sch. 12 para. 4(a)