OpenLegislation

Division C.1 Please complete table below taking into account the following

United Kingdom

Original text. Later amendments are not shown.

  1. (1)

    Ineligible costs comprise (i) expenditure outside the eligibility period, (ii) expenditure ineligible under applicable EU and national rules, (iii) other expenditure not presented for co-financing. NB: The starting date for eligibility of expenditure is the date of submission of the operational programme to the Commission or 1 January 2014, whichever is the earlierf1.

  2. (2)

    Contingencies should not exceed 10 % of total cost net of contingencies. These contingencies may be included in the total eligible costs used to calculate the planned contribution of the funds.

  3. (3)

    A price adjustment may be included, where relevant, to cover expected inflation where the eligible cost values are in constant prices.

  4. (4)

    Recoverable VAT is ineligible. Where VAT is considered eligible, please give reasons.

  5. (5)

    Total cost must include all costs incurred for the project, from planning to supervision and must include VAT regardless of whether it is recoverable or not.

  6. (6)

    The purchase of land not built on and land built on in the amount exceeding 10 % of the total eligible expenditure for the operation concerned in accordance with Article 69(3)(b) of Regulation (EU) No 1303/2013. In exceptional and duly justified cases, a higher percentage may be permitted for operations concerning environmental conservation.

  7. (7)

    Total eligible cost before taking into account of the requirements set out in Article 61 of Regulation (EU) No 1303/2013.

EURTotal cost(A)Ineligible costs (1)(B)Eligible costs(C) = (A) – (B)Percentage of total eligible costs
Input Input Calculated Calculated
1Planning/design fees <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
2Land purchase <type='N' input='M'> <type='N' input='M'> (6) <type='N' input='G'> <type='P' input='G'>
3Building and construction <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
4Plant and machinery or equipment <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
5Contingencies (2) <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
6Price adjustment (if applicable) (3) <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
7Publicity <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
8Supervision during construction implementation <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
9Technical assistance <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
10 Sub-TOTAL <type='N' input='G'> <type='N' input='G'> <type='N' input='G'> <type='P' input='G'>
11(VAT (4)) <type='N' input='M'> <type='N' input='M'> <type='N' input='G'> <type='P' input='G'>
12 TOTAL <type='N' input='G'> (5) <type='N' input='G'> <type='N' input='G'> (7) <type='P' input='G'>

Please provide the exchange rate and the reference (where applicable)

< type='S' maxlength='875' input='M'>

If you have any comments regarding any of the items above (e.g. no contingencies envisaged, eligible VAT), please note them below.

< type='S' maxlength='1750' input='M'>

Annotations

Footnotes

f1

Unless project specific rules must apply e.g. state aid.