Division 1.3.2
United Kingdom
During the test, the following requirements shall be satisfied:
- 1.3.2.1.
The pressure in the reservoirs at the beginning of the test shall be 850 kPa.
- 1.3.2.2.
The supply line shall be blocked off; in addition, the auxiliary equipment reservoirs shall be isolated.
- 1.3.2.3.
The reservoir shall not be replenished during the test.
- 1.3.2.4.
At each brake application, the pressure in the control line shall be 750 kPa.
- 1.3.2.5.
At each brake application, the digital demand value in the electric control line shall be corresponding to a pneumatic pressure of 750 kPa.