Article 60 General provisions
United Kingdom
The provisions of this Chapter shall apply to new DC-connected power park modules only.
The DC-connected power park module owner shall demonstrate to the relevant system operator its compliance with the requirements referred to in Title III at the respective connection points by successfully completing the operational notification procedure for connection of the DC-connected power park module in accordance with Articles 61 through to 66.
The relevant system operator shall specify further details of the operational notification procedure and make those details publically available.
The operational notification procedure for connection for each new DC-connected power park module shall comprise:
energisation operational notification (EON);
interim operational notification (ION); and
final operational notification (FON).