Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (Text with EEA relevance)

EU Regulation 2016/1447 · Adopted 26 August 2016 · Extends to United Kingdom

Original text. legislation.gov.uk does not revise this item, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Commission Regulation (EU) 2016/1447

of 26 August 2016

establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules

(Text with EEA relevance)

THE EUROPEAN COMMISSION,

Having regard to the Treaty on the Functioning of the European Union,

Having regard to Regulation (EC) No 714/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the network for cross-border exchanges in electricity and repealing Regulation (EC) No 1228/2003f1, and in particular Article 6(11) thereof,

Whereas:

(1)

The swift completion of a fully functioning and interconnected internal energy market is crucial to maintaining security of energy supply, increasing competitiveness and ensuring that all consumers can purchase energy at affordable prices.

(2)

Regulation (EC) No 714/2009 sets out non-discriminatory rules governing access to the network for cross-border exchanges in electricity with a view to ensuring the proper functioning of the internal market in electricity. In addition Article 5 of Directive 2009/72/EC of the European Parliament and of the Councilf2 requires that Member States or, where Member States have so provided, regulatory authorities ensure, inter alia, that objective and non-discriminatory technical rules are developed which establish minimum technical design and operational requirements for the connection to the system. Where requirements constitute terms and conditions for connection to national networks, Article 37(6) of the same Directive requires regulatory authorities to be responsible for fixing or approving at least the methodologies used to calculate or establish them. In order to provide system security within the interconnected transmission system, it is essential to establish a common understanding of the requirements for High-Voltage Direct Current (HVDC) systems and direct current-connected power park modules (DC-connected power park modules). Those requirements that contribute to maintaining, preserving and restoring system security in order to facilitate proper functioning of the internal electricity market within and between synchronous areas, and to achieve cost efficiencies, should be regarded as cross-border network issues and market integration issues.

(3)

Harmonised rules for grid connection for HVDC systems and DC-connected power park modules should be set out in order to provide a clear legal framework for grid connections, facilitate Union-wide trade in electricity, ensure system security, facilitate the integration of renewable electricity sources, increase competition and allow more efficient use of the network and resources, for the benefit of consumers.

(4)

System security depends partly on the technical capabilities of HVDC systems and DC-connected power park modules. Therefore regular coordination at the level of the transmission and distribution networks and adequate performance of the equipment connected to the transmission and distribution networks with sufficient robustness to cope with disturbances and to help to prevent any major disruption or to facilitate restoration of the system after a collapse are fundamental prerequisites.

(5)

Secure system operation is only possible if there is close cooperation between owners of HVDC systems and DC-connected power park modules and system operators. In particular, the functioning of the system under abnormal operating conditions depends on the response of the HVDC systems and DC-connected power park modules to deviations from the reference 1 per unit (pu) values of voltage and nominal frequency. In the context of system security, the networks and the HVDC systems and DC-connected power park modules should be considered as one entity from a system engineering point of view, given that those parts are interdependent. Therefore, as a prerequisite for grid connection, relevant technical requirements should be set for HVDC systems and DC-connected power park modules.

(6)

Regulatory authorities should consider the reasonable costs effectively incurred by system operators in the implementation of this Regulation when fixing or approving transmission or distribution tariffs or their methodologies or when approving the terms and conditions for connection and access to national networks in accordance with Article 37(1) and (6) of Directive 2009/72/EC and with Article 14 of Regulation (EC) No 714/2009.

(7)

Different synchronous electricity systems in the Union have different characteristics which need to be taken into account when setting the requirements for HVDC systems and DC-connected power park modules. It is therefore appropriate to consider regional specificities when establishing network connection rules as required by Article 8(6) of Regulation (EC) No 714/2009.

(8)

In view of the need to provide regulatory certainty, the requirements of this Regulation should apply to new HVDC systems and new DC-connected power park modules but should not apply to HVDC systems and DC-connected power park modules already existing or at an advanced stage of planning but not yet completed unless the relevant regulatory authority or Member State decides otherwise based on evolution of system requirements and a full cost-benefit analysis, or where there has been substantial modernisation of those facilities.

(9)

Due to its cross-border impact, this Regulation should aim at the same frequency-related requirements for all voltage levels, at least within a synchronous area. That is necessary because, within a synchronous area, a change in frequency in one Member State would immediately impact frequency and could damage equipment in all other Member States.

(10)

To ensure system security, it should be possible for HVDC systems and DC-connected power park modules in each synchronous area of the interconnected system to remain connected to the system for specified frequency and voltage ranges.

(11)

Voltage ranges should be coordinated between interconnected systems because they are crucial to secure planning and operation of a power system within a synchronous area. Disconnections because of voltage disturbances have an impact on neighbouring systems. Failure to specify voltage ranges could lead to widespread uncertainty in planning and operation of the system with respect to operation beyond normal operating conditions.

(12)

Appropriate and proportionate compliance testing should be introduced so that system operators can ensure operational security. In accordance with Article 37(1)(b) of Directive 2009/72/EC, regulatory authorities are responsible for ensuring that system operators are compliant with this Regulation.

(13)

The regulatory authorities, Member States and system operators should ensure that, in the process of developing and approving the requirements for network connection, they are harmonised to the extent possible, in order to ensure full market integration. Established technical standards should be taken into particular consideration in the development of connection requirements.

(14)

A process for derogating from the rules should be set out in this Regulation to take into account local circumstances where exceptionally, for example, compliance with those rules could jeopardise the stability of the local network or where the safe operation of an HVDC system or DC-connected power park module might require operating conditions that are not in line with this Regulation.

(15)

In the case of DC-connected power park modules, new modules could, in the future form part of a meshed off-shore grid connecting to more than one synchronous area. In this case, certain technical requirements should be set in order to maintain system security and ensure that future meshed networks can be developed cost-effectively. However, for certain requirements, DC-connected power park modules should only be required to fit the equipment needed for system security at the time it becomes necessary.

(16)

Therefore, the owners of DC-connected power park modules which are, or will be, connected to one synchronous area with a radial connection should have the possibility to apply, via an expedited process, for derogations to requirements that will only be needed where the power park modules become connected to a meshed grid and which take account of case-by-case circumstances. They should also be informed as early as possible whether they qualify for a derogation for the purposes of their investment decision-making.

(17)

Subject to approval by the relevant regulatory authority, or other authority where applicable in a Member State, system operators should be allowed to propose derogations for certain classes of HVDC systems and DC-connected power park modules.

(18)

This Regulation has been adopted on the basis of Regulation (EC) No 714/2009 which it supplements and of which it forms an integral part. References to Regulation (EC) No 714/2009 in other legal acts should be understood as also referring to this Regulation.

(19)

The measures provided for in this Regulation are in accordance with the opinion of the Committee referred to in Article 23(1) of Regulation (EC) No 714/2009,

HAS ADOPTED THIS REGULATION:

Annotations to the whole text

Footnotes

f1

OJ L 211, 14.8.2009, p. 15.

f2

Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC (OJ L 211, 14.8.2009, p. 55).

Contents

  1. Title I: GENERAL PROVISIONS
  2. 1Subject matter
  3. 2Definitions
  4. 3Scope of application
  5. 4Application to existing HVDC systems and DC-connected power park modules
  6. 5Regulatory aspects
  7. 6Multiple TSOs
  8. 7Recovery of costs
  9. 8Public consultation
  10. 9Stakeholder involvement Repealed
  11. 10Confidentiality obligations
  12. Title II: GENERAL REQUIREMENTS FOR HVDC CONNECTIONS
  13. Chapter 1: Requirements for active power control and frequency support
  14. 11Frequency ranges
  15. 12Rate-of-change-of-frequency withstand capability
  16. 13Active power controllability, control range and ramping rate
  17. 14Synthetic inertia
  18. 15Requirements relating to frequency sensitive mode, limited frequency sensitive mode overfrequency and limited frequency sensitive mode underfrequency
  19. 16Frequency control
  20. 17Maximum loss of active power
  21. Chapter 2: Requirements for reactive power control and voltage support
  22. 18Voltage ranges
  23. 19Short circuit contribution during faults
  24. 20Reactive power capability
  25. 21Reactive power exchanged with the network
  26. 22Reactive power control mode
  27. 23Priority to active or reactive power contribution
  28. 24Power quality
  29. Chapter 3: Requirements for fault ride through capability
  30. 25Fault ride through capability
  31. 26Post fault active power recovery
  32. 27Fast recovery from DC faults
  33. Chapter 4: Requirements for control
  34. 28Energisation and synchronisation of HVDC converter stations
  35. 29Interaction between HVDC systems or other plants and equipment
  36. 30Power oscillation damping capability
  37. 31Subsynchronous torsional interaction damping capability
  38. 32Network characteristics
  39. 33HVDC system robustness
  40. Chapter 5: Requirements for protection devices and settings
  41. 34Electrical protection schemes and settings
  42. 35Priority ranking of protection and control
  43. 36Changes to protection and control schemes and settings
  44. Chapter 6: Requirements for power system restoration
  45. 37Black start
  46. Title III: REQUIREMENTS FOR DC-CONNECTED POWER PARK MODULES AND REMOTE-END HVDC CONVERTER STATIONS
  47. Chapter 1: Requirements for DC-connected power park modules
  48. 38Scope
  49. 39Frequency stability requirements
  50. 40Reactive power and voltage requirements
  51. 41Control requirements
  52. 42Network characteristics
  53. 43Protection requirements
  54. 44Power quality
  55. 45General system management requirements applicable to DC-connected power park modules
  56. Chapter 2: Requirements for remote-end HVDC converter stations
  57. 46Scope
  58. 47Frequency stability requirements
  59. 48Reactive power and voltage requirements
  60. 49Network characteristics
  61. 50Power quality
  62. Title IV: INFORMATION EXCHANGE AND COORDINATION
  63. 51Operation of HVDC systems
  64. 52Parameters and settings
  65. 53Fault recording and monitoring
  66. 54Simulation models
  67. Title V: OPERATIONAL NOTIFICATION PROCEDURE FOR CONNECTION
  68. Chapter 1: Connection of new HVDC systems
  69. 55General provisions
  70. 56EON for HVDC systems
  71. 57ION for HVDC systems
  72. 58FON for HVDC systems
  73. 59Limited operational notification for HVDC systems/derogations
  74. Chapter 2: Connection of new DC-connected power park modules
  75. 60General provisions
  76. 61EON for DC-connected power park modules
  77. 62ION for DC-connected power park modules
  78. 63FON for DC-connected power park modules
  79. 64Limited operational notification for DC-connected power park modules
  80. Chapter 3: Cost benefit analysis
  81. 65Identification of costs and benefits of application of requirements to existing HVDC systems or DC-connected power park modules
  82. 66Principles of cost-benefit analysis
  83. Title VI: COMPLIANCE
  84. Chapter 1: Compliance monitoring
  85. 67Common provisions for compliance testing
  86. 68Common provisions on compliance simulation
  87. 69Responsibility of the HVDC system owner and DC-connected power park module owner
  88. 70Tasks of the relevant system operator
  89. Chapter 2: Compliance testing
  90. 71Compliance testing for HVDC systems
  91. 72Compliance testing for DC-connected power park modules and remote-end HVDC converter units
  92. Chapter 3: Compliance simulations
  93. 73Compliance simulations for HVDC systems
  94. 74Compliance simulations for DC-connected power park modules and remote-end HVDC converter units
  95. Chapter 4: Non-binding guidance and monitoring of implementation Repealed
  96. 75Non-binding guidance on implementation Repealed
  97. 76Monitoring Repealed
  98. Title VII: DEROGATIONS
  99. 77Power to grant derogations
  100. 78General provisions
  101. 79Request for derogations by an HVDC system owner or DC-connected power park module owner
  102. 80Request for a derogation by a relevant system operator or relevant TSO
  103. 81Request for derogations from the provisions of Title III by a DC-connected power park module owner
  104. 82Register of derogations from the requirements of this Regulation
  105. 83Monitoring of derogations
  106. Title VIII: FINAL PROVISIONS
  107. 84Amendment of contracts and general terms and conditions
  108. 85HVDC System or DC-connected power park modules connecting with synchronous areas or control areas not bound by EU legislation
  109. 86Entry into force
  110. Signature
  111. Annex IFrequency ranges referred to in Article 11
  112. Annex II: Requirements applying to frequency sensitive mode, limited frequency sensitive mode overfrequency and limited frequency sensitive mode underfrequency
  113. Frequency sensitive mode
  114. 1When operating in frequency sensitive mode (FSM):
  115. BLimited frequency sensitive mode overfrequency
  116. CLimited frequency sensitive mode underfrequency
  117. Annex IIIVoltage ranges referred to in Article 18
  118. Annex IVRequirements for U-Q/Pmax-profile referred to in Article 20
  119. Annex VVoltage-against-time-profile referred to in Article 25
  120. Annex VIFrequency ranges and time periods referred to in Article 39(2)(a)
  121. Annex VIIVoltage ranges and time periods referred to in Article 40
  122. Annex VIIIReactive power and voltage requirements referred to in Article 48