Commission Regulation (EU) 2016/1719 of 26 September 2016 establishing a guideline on forward capacity allocation (Text with EEA relevance) (revoked)

EU Regulation 2016/1719 · Adopted 26 September 2016 · Extends to United Kingdom

Original text. legislation.gov.uk does not revise this item, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Commission Regulation (EU) 2016/1719

of 26 September 2016

establishing a guideline on forward capacity allocation

(Text with EEA relevance) (revoked)

F1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Annotations to the whole text

Textual amendments

F1

Regulation revoked (E.W.S.) (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 5(1)(b) (as amended by S.I. 2020/1016, regs. 1(2), 5(2)); 2020 c. 1, Sch. 5 para. 1(1)

Contents

  1. Title I: GENERAL PROVISIONS Repealed
  2. 1Subject matter and scope Repealed
  3. 2Definitions Repealed
  4. 3Objectives of forward capacity allocation Repealed
  5. 4Adoption of terms and conditions or methodologies Repealed
  6. 5Stakeholder involvement Repealed
  7. 6Consultation Repealed
  8. 7Confidentiality obligations Repealed
  9. Title II: REQUIREMENTS FOR TERMS, CONDITIONS AND METHODOLOGIES Repealed
  10. Chapter 1: Forward capacity calculation Repealed
  11. General requirements Repealed
  12. 8Capacity calculation regions Repealed
  13. 9Capacity calculation time frames Repealed
  14. Capacity calculation methodology Repealed
  15. 10Capacity calculation methodology Repealed
  16. 11Reliability margin methodology Repealed
  17. 12Methodologies for operational security limits and contingencies Repealed
  18. 13Generation shift keys methodology Repealed
  19. 14Methodology for remedial actions Repealed
  20. 15Cross-zonal capacity validation methodology Repealed
  21. 16Methodology for splitting long-term cross-zonal capacity Repealed
  22. Common grid model Repealed
  23. 17Generation and load data provision methodology Repealed
  24. 18Common grid model methodology Repealed
  25. 19Scenarios Repealed
  26. 20Individual grid model Repealed
  27. Capacity calculation process Repealed
  28. 21General provisions Repealed
  29. 22Creation of a common grid model Repealed
  30. 23Regional calculations of long-term cross-zonal capacities Repealed
  31. 24Validation and delivery of cross-zonal capacity and split cross-zonal capacity Repealed
  32. 25Coordinated curtailment of cross-zonal capacity Repealed
  33. Biennial report on capacity calculation Repealed
  34. 26Biennial report on capacity calculation and allocation Repealed
  35. Chapter 2: Bidding zones Repealed
  36. 27General provisions Repealed
  37. Chapter 3: Forward capacity allocation Repealed
  38. General provisions Repealed
  39. 28General principles Repealed
  40. 29Input and results Repealed
  41. Options for cross-zonal transmission risk hedging Repealed
  42. 30Decision on cross-zonal risk hedging opportunities Repealed
  43. 31Regional design of long-term transmission rights Repealed
  44. 32Physical transmission rights Repealed
  45. 33Financial transmission rights — options Repealed
  46. 34Financial transmission rights — obligations Repealed
  47. 35Principles for long-term transmission rights remuneration Repealed
  48. Nomination procedures for physical transmission rights Repealed
  49. 36General provisions for physical transmission rights nomination Repealed
  50. Processes and operation Repealed
  51. 37Terms and conditions for participation in the forward capacity allocation Repealed
  52. 38Submission of input data to the single allocation platform Repealed
  53. 39Operation of the forward capacity allocation Repealed
  54. 40Pricing of the long-term transmission rights Repealed
  55. 41Financial requirements and settlement Repealed
  56. 42Establishment of fallback procedures Repealed
  57. 43Return of long-term transmission rights Repealed
  58. 44Transfer of long-term transmission rights Repealed
  59. 45Delivery of results Repealed
  60. 46Initiation of fallback procedures Repealed
  61. 47Publication of market information Repealed
  62. Chapter 4: Single allocation platform Repealed
  63. 48Establishment Repealed
  64. 49Functional requirements Repealed
  65. 50General tasks Repealed
  66. Chapter 5: Harmonised allocation rules Repealed
  67. 51Introduction of harmonised allocation rules Repealed
  68. 52Requirements for the harmonised allocation rules Repealed
  69. Chapter 6: Firmness of allocated cross-zonal capacity Repealed
  70. 53General firmness provisions Repealed
  71. 54Definition of caps Repealed
  72. 55Compensation rules Repealed
  73. 56Firmness in the event of force majeure Repealed
  74. Chapter 7: Congestion income distribution Repealed
  75. 57Congestion income distribution methodology Repealed
  76. Chapter 8: Cost recovery Repealed
  77. 58General provisions on cost recovery Repealed
  78. 59Cost of establishing, developing and operating the single allocation platform Repealed
  79. 60Cost of establishing and operating the coordinated capacity calculation process Repealed
  80. 61Cost of ensuring firmness and remuneration of long-term transmission rights Repealed
  81. Title III: DELEGATION OF TASKS AND MONITORING Repealed
  82. 62Delegation of tasks Repealed
  83. 63Monitoring Repealed
  84. Title IV: FINAL PROVISIONS Repealed
  85. 64Entry into force Repealed
  86. Signature

1Subject matter and scopeF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

2DefinitionsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3Objectives of forward capacity allocationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4Adoption of terms and conditions or methodologiesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

5Stakeholder involvementF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

6ConsultationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

7Confidentiality obligationsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

8Capacity calculation regionsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

9Capacity calculation time framesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

10Capacity calculation methodologyF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

11Reliability margin methodologyF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

12Methodologies for operational security limits and contingenciesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

13Generation shift keys methodologyF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

14Methodology for remedial actionsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

15Cross-zonal capacity validation methodologyF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

16Methodology for splitting long-term cross-zonal capacityF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

17Generation and load data provision methodologyF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

18Common grid model methodologyF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

19ScenariosF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

20Individual grid modelF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

21General provisionsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

22Creation of a common grid modelF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

23Regional calculations of long-term cross-zonal capacitiesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

24Validation and delivery of cross-zonal capacity and split cross-zonal capacityF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

25Coordinated curtailment of cross-zonal capacityF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

26Biennial report on capacity calculation and allocationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

27General provisionsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

28General principlesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

29Input and resultsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

30Decision on cross-zonal risk hedging opportunitiesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

31Regional design of long-term transmission rightsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

32Physical transmission rightsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

33Financial transmission rights — optionsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

34Financial transmission rights — obligationsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

35Principles for long-term transmission rights remunerationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

36General provisions for physical transmission rights nominationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

37Terms and conditions for participation in the forward capacity allocationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

38Submission of input data to the single allocation platformF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

39Operation of the forward capacity allocationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

40Pricing of the long-term transmission rightsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

41Financial requirements and settlementF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

42Establishment of fallback proceduresF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

43Return of long-term transmission rightsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

44Transfer of long-term transmission rightsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

45Delivery of resultsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

46Initiation of fallback proceduresF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

47Publication of market informationF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

48EstablishmentF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

49Functional requirementsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

50General tasksF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

51Introduction of harmonised allocation rulesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

52Requirements for the harmonised allocation rulesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

53General firmness provisionsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

54Definition of capsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

55Compensation rulesF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

56Firmness in the event of force majeureF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

57Congestion income distribution methodologyF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

58General provisions on cost recoveryF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

59Cost of establishing, developing and operating the single allocation platformF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

60Cost of establishing and operating the coordinated capacity calculation processF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

61Cost of ensuring firmness and remuneration of long-term transmission rightsF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

62Delegation of tasksF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

63MonitoringF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

64Entry into forceF1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Signature