OpenLegislation

Article 143 Frequency restoration process

United Kingdom

Original text. Later amendments are not shown.

F11.

The control target of the FRP shall be to regulate the FRCE towards zero within the time to restore frequency.

2.

The FRCE is:

(a)

the ACE of an LFC area, where there is more than one LFC area in a synchronous area; or

(b)

the frequency deviation, where one LFC area corresponds to the LFC block and the synchronous area.

3.

The ACE of a LFC area shall be calculated as the sum of the product of the K-Factor of the LFC area with the frequency deviation plus de subtraction of:

(a)

the total interconnector and virtual tie-line active power flow; and

(b)

the control program in accordance with Article 136.

F24.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F35.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Annotations

Textual amendments

F1

Art. 143(1) substituted (E.W.S.) (31.12.2020) by The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 93(2) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)

F2

Art. 143(4) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 93(3) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)

F3

Art. 143(5) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 93(3) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)